Progress
 
 
Project Details
DAR-2022-000275
MSPDCL-STATEPLAN-092
Supply and Erection of existing 130W LED Street Lights on 8m GI Octagonal Pole and for replacement of the old 250/150W HPSV Lamps
21/04/2021
POWER (MSPDCL)
Imphal
83.10
0.00
State Plan
Complete
1
24.81484,93.94393
Supply and Erection of existing 130W LED Street Lights on 8m GI Octagonal Pole and for replacement of the old 250/150W HPSV Lamps. (Turn Key works of Reovation) M/S Meetei Construction Pvt. Ltd. Soibam Leikai, Imphal-East
Progress Update : 24/03/2022
Complete
1
Rajesh
24.81484,93.94393
24.7507169,93.9334421
7.2080013896336
0
High mast M U Canchipur

Progress Update : 24/03/2022
Complete
1
Rajesh
24.81484,93.94393
24.7534731,93.9344286
6.890443061863
0
Street lamp singjamei to M U Canchipur

Progress Update : 23/03/2022
Complete
1
Rajesh
24.81484,93.94393
24.8405841,93.9411091
2.876595322811
0
Chingmeirong khongnang karak to koirengei

Progress Update : 23/03/2022
Complete
1
Rajesh
24.81484,93.94393
24.8123478,93.936386
0.81023275136357
0
Street lamp kangla western gate to khuyathong

Progress Update : 23/03/2022
Complete
1
Rajesh
24.81484,93.94393
24.8076437,93.9332372
1.3434597347205
0
Street lamp fly over

Progress Update : 23/03/2022
Complete
1
Rajesh
24.81484,93.94393
24.8049701,93.9283877
1.9144171336879
0
Street lamp waheng leikaito NRL Sagolband

Progress Update : 23/03/2022
Completed
1
Rajesh
24.81484,93.94393
24.8202481,93.9445739
0.6048254238952
0
North AOC high mast

Progress Update : 23/03/2022
Completed
1
Rajesh
24.81484,93.94393
24.8262577,93.9443311
1.2701743900532
0
KHONGNANG KARAK HIGH MAST

Progress Update : 23/03/2022
Complete
1
Rajesh
24.81484,93.94393
24.8025317,93.945287
1.3753908001274
0
Street lamp place gate CM Gate