Progress
 
 
Project Details
DAR-2022-000142
TAOTHONG AYUNGBA PRIMARY SCHOOL
BOYS TOILET
2021-01-07
Edu (S) - SSA & RMSA
Imphal-West
3.50
1.35
CSS / CPS
Construction up to finishing level
Final installment
24.814212172849558,93.87286883068846
CONSTRUCTION OF BOYS TOILET AT TAOTHONG AYUNGBA PRIMARY SCHOOL
Progress Update : 2022-02-11
Construction up to finishing level
Final installment
ssaimphalwest
24.814212172849558,93.87286883068846
24.8144567,93.8728738
0.027193636430214
Approved
2022-05-26 07:52:27
ssarmsaadmin
0
Construction of boys toilet

Progress Update : 2022-02-11
Construction up to finishing level
Final installment
ssaimphalwest
24.814212172849558,93.87286883068846
24.8143762,93.8728255
0.018755247034345
Approved
2022-05-26 07:52:45
ssarmsaadmin
0
Construction of boys toilet

Progress Update : 2022-02-11
Construction up to finishing level
Final installment
ssaimphalwest
24.814212172849558,93.87286883068846
24.8143762,93.8728255
0.018755247034345
Approved
2022-05-26 07:53:03
ssarmsaadmin
0
Construction of boys toilet

Progress Update : 2022-02-11
Construction up to finishing level
Final installment
ssaimphalwest
24.814212172849558,93.87286883068846
24.8162228,93.8745981
0.28361543571527
Approved
2022-05-26 07:53:23
ssarmsaadmin
0
Construction of boys toilet

Progress Update : 2022-02-11
Construction up to finishing level
Final installment
ssaimphalwest
24.814212172849558,93.87286883068846
24.8162228,93.8745981
0.28361543571527
Approved
2022-05-26 07:53:44
ssarmsaadmin
0
Construction of boys toilet

Progress Update : 2022-02-11
Construction up to finishing level
Final installment
ssaimphalwest
24.814212172849558,93.87286883068846
24.8162228,93.8745981
0.28361543571527
Approved
2022-05-26 07:54:04
ssarmsaadmin
0
Construction of boys toilet

Foundation & Inauguration
-
-
-

-
-
-