Progress
 
 
Project Details
DAR-2022-000031
BD-II/AE-IV/T VII No.1 Majorkhul.
Major renovation of Govt. Qtr. No.T-VII No.1 occupied by Hon'ble MLA L Rameshwor Meetei,Majorkhul.
24/12/2019
PWD
Imphal-West
58.99
33
State Plan
Completed
Final
24.81216140398276,93.93647188252565
Approach road, compound wall, constn. of toilet, over head tank, side wall, line drain.....etc.
Progress Update : 21/10/2024
Completed
Final
Sudip21
24.81216140398276,93.93647188252565
24.8124972,93.9385278
0.21082668377544
33
tile flooring

Progress Update : 21/10/2024
Completed
Final
Sudip21
24.81216140398276,93.93647188252565
24.8126287,93.9384666
0.20791442450032
33
Main building

Progress Update : 21/10/2024
completed
Final
Sudip21
24.81216140398276,93.93647188252565
24.8126649,93.9385253
0.21467022592314
33
yard flooring

Progress Update : 21/10/2024
completed
Final
Sudip21
24.81216140398276,93.93647188252565
24.8126678,93.9386019
0.22222418233647
33
compound wall

Progress Update : 06/10/2022
100%
II
nh1so3b
24.81216140398276,93.93647188252565
24.8125934,93.9383436
0.19491486817106
0
Compound wall

Progress Update : 06/10/2022
100%
II
nh1so3b
24.81216140398276,93.93647188252565
24.8125874,93.9383323
0.193645520562
0
Yard flooring

Progress Update : 06/10/2022
100%
II
nh1so3b
24.81216140398276,93.93647188252565
24.8124252,93.9383173
0.18854495404677
0
Tiles flooring (Main building) kitchen

Progress Update : 06/10/2022
100%
II
nh1so3b
24.81216140398276,93.93647188252565
24.8124252,93.9383173
0.18854495404677
0
Tiles flooring (Main building)

Progress Update : 06/10/2022
100%
II
nh1so3b
24.81216140398276,93.93647188252565
24.8146403,93.9388019
0.3623102438971
0
Waiting shed

Progress Update : 06/10/2022
100%
II
nh1so3b
24.81216140398276,93.93647188252565
24.8146403,93.9388019
0.3623102438971
0
Front main building

Progress Update : 11/01/2022
60℅
I
nh1so3b
24.81216140398276,93.93647188252565
24.8148045,93.9382422
0.34393397130544
0
Yard flooring

Progress Update : 11/01/2022
60℅
I
nh1so3b
24.81216140398276,93.93647188252565
24.8119489,93.9392333
0.27969747733886
0
Main building (Front View)

Progress Update : 11/01/2022
60℅
I
nh1so3b
24.81216140398276,93.93647188252565
24.8119489,93.9392333
0.27969747733886
0
Main building (drawing room)

Progress Update : 11/01/2022
60℅
I
nh1so3b
24.81216140398276,93.93647188252565
24.8119489,93.9392333
0.27969747733886
0
Main building