Progress
 
 
Project Details
DAR-2021-001893
Moijing Upper Primary School, SMDC, 2017-18
Upper Primary School Moijing UPS
13/03/2019
Edu (S) - SSA & RMSA
Thoubal
29.79
11.46
CSS / CPS
Completef
Completion
24.652854057210625,93.95991083610689
Construction of Upper Primary School at Moijing Upper Primary School approved in 2017-18.Construction of 3 (three) classroom with IEI
Progress Update : 22/11/2021
Completef
Completion
ssatblkak
24.652854057210625,93.95991083610689
24.65277435,93.9599312
0.0090985051150452
0
Construction of Upper Primary School at Moijing Upper Primary School

Progress Update : 22/11/2021
Completef
Completion
ssatblkak
24.652854057210625,93.95991083610689
24.65281132,93.95991651
0.0047862413683838
0
Construction of Upper Primary School at Moijing Upper Primary School