DAR-2021-001854
WILLONG HGH SCHOOL 5 STAFF QUARTER
Construction of 5 S.Q Eng. wing
31/10/2019
Edu (S) - SSA & RMSA
Senapati
74.23
23.75
CSS / CPS
25.47487875010761,93.96354933261873
THE ON GOING CONSTRUCTION OF 5 RESIDENTIAL STAFF QUARTER UNDER ENG. WING HAVE REACHED UPTO ROOFING LEVEL, PLASTER WORK IS IN PROGRESS. DUE TO LESS OF SPACE CONSTUCTION WAS DONE IN TWO PLACES, THE DISTNCE BETWEEN TWO SITE IS AROUNG 100M