Progress
 
 
Project Details
DAR-2021-001765
COSFOM/EPA/LANGDANG
COSFOM/EPA/LANGDANG
2020-06-27
FOREST
Ukhrul
4.12
4.12
KFW
Completed
1
25.10530975081921,94.40059903690948
CONSTRUCTION OF WATER RESERVOIR/TANK AT LANGDANG VILLAGE
Progress Update : 2021-11-21
Completed
1
rfoukhrul
25.10530975081921,94.40059903690948
25.1054232,94.4007696
0.021308090115241
Approved
2021-11-21 11:47:00
cosfom_ukhrul
4.12
Water Tank

Progress Update : 2021-10-04
Completed
1
rfoukhrul
25.10530975081921,94.40059903690948
25.1054331,94.4003625
0.027482733415305
Approved
2021-10-04 11:06:35
cosfom_ukhrul
4.12
EPA-Water reservior tank 15000 ltr

Progress Update : 2021-10-04
Completed
1
rfoukhrul
25.10530975081921,94.40059903690948
25.1053681,94.4006392
0.0076453134404643
Approved
2021-10-04 11:06:48
cosfom_ukhrul
4.12
EPA-Water reservior tank 15000 ltr

Foundation & Inauguration
-
-
-

-
-
-