Progress
 
 
Project Details
DAR-2017-000147
WRD-IMW-01
Construction of road side drain of the approach road from Singda Bazar to irrigation rest house
2014-11-14
Water Resources Department (WRD)
Kangpokpi
38.85
31.64
State Plan
Completed
Final Phase
24.87918586327845,93.80456078052543
The project has been constructed to catch the surface run-off from the hill slope to prevent eroding the approach road.
Progress Update : 2017-12-18
Completed
Final Phase
IMD-2
24.87918586327845,93.80456078052543
24.8761443,93.8073133
0.43756532350157
Approved
2017-12-18 08:44:35
approverifcd
0
Construction of road side drain along the approach road to Irrigation Rest House at Singda Dam.

Foundation & Inauguration
-
-
-

-
-
-