Project Details
DAR-2017-000011
FOR/CONST/ORCHID/01
DEVELOPMENT OF ORCHID PRESERVATION CENTRE AT KHONGHAMPAT, MANIPUR
28/02/2014
FOREST
Imphal-West
186.21
10
NEC
Completed
Phase-1
24.881069216715037,93.9071767330172
DEVELOPMENT OF ORCHID PRESERVATION CENTRE AT KHONGHAMPAT, MANIPUR
Progress Update : 02/11/2017
Completed
Phase-1
orchid
24.881069216715037,93.9071767330172
24.8859508,93.9036813
0.64724067988969
1.66
Construction visitors rest shed

Progress Update : 02/11/2017
Completed
Phase-1
orchid
24.881069216715037,93.9071767330172
24.8858214,93.9084721
0.54430829776285
1.66
Construction visitors rest shed

Progress Update : 02/11/2017
Completed
Phase-1
orchid
24.881069216715037,93.9071767330172
24.8805492,93.9070534
0.059143597437512
1.66
Construction visitors rest shed

Progress Update : 02/11/2017
Completed (500 RM)
Phase-1
orchid
24.881069216715037,93.9071767330172
24.8814213,93.9076307
0.060244525533765
65.85
Construction of pucca topping with side drain with railing

Progress Update : 02/11/2017
completed
Phase-1
orchid
24.881069216715037,93.9071767330172
24.8858214,93.9084721
0.54430829776285
1.66
Construction of visitors rest shed

Progress Update : 02/11/2017
Completed
Phase-1
orchid
24.881069216715037,93.9071767330172
24.8812626,93.9076706
0.054258456079159
3.325
Construction of drinking water facility with overhead tank

Progress Update : 02/11/2017
Completed
Phase-1
orchid
24.881069216715037,93.9071767330172
24.8812879,93.9078301
0.070247072882807
1.2
Propagation of orchids in pots

Progress Update : 02/11/2017
Completed
Phase-1
orchid
24.881069216715037,93.9071767330172
24.8858214,93.9084721
0.54430829776285
1.2
Propagation of orchids in pots

Progress Update : 02/11/2017
Completed
Phase-1
orchid
24.881069216715037,93.9071767330172
24.8858214,93.9084721
0.54430829776285
1.66
Construction of rest shed

Progress Update : 02/11/2017
80 % Completed
Phase-1
orchid
24.881069216715037,93.9071767330172
24.8858214,93.9084721
0.54430829776285
65.85
Construction of pucca toping

Progress Update : 02/11/2017
100 % Completed
Phase-III & final installment
orchid
24.881069216715037,93.9071767330172
24.8813594,93.9072964
0.034449392913578
37.33
Construction of pucca topping (400RM)

Progress Update : 02/11/2017
80 pc completed
Phase-1
orchid
24.881069216715037,93.9071767330172
24.8988401,93.8933243
2.4200107813668
65.85
Construction of pucca toping

Progress Update : 02/11/2017
5 nos of Sign Board
Phase-1
orchid
24.881069216715037,93.9071767330172
24.8814884,93.9072682
0.047513091436534
1
Construction of sign board

Progress Update : 02/11/2017
5 nos of Sign Board
Phase-1
orchid
24.881069216715037,93.9071767330172
24.8813393,93.907208
0.03019558372411
1
Construction of sign board

Progress Update : 02/11/2017
Completed
Phase-1
orchid
24.881069216715037,93.9071767330172
24.8858214,93.9084721
0.54430829776285
1.88
Construction of parking for visitors

Progress Update : 02/11/2017
90 percent completed
Phase-1
orchid
24.881069216715037,93.9071767330172
24.8808136,93.9065229
0.071815270202746
50.5
Construction of boundary wall

Progress Update : 02/11/2017
90 percent completed
Phase-1
orchid
24.881069216715037,93.9071767330172
24.8832101,93.9055089
0.29149066302101
50.5
Construction of boundary wall

Progress Update : 24/10/2017
5 nos of sign board Completed
Phase - 1
orchid
24.881069216715037,93.9071767330172
24.8919168,93.9115225
1.2833187964272
1
Erection of sign boards

Progress Update : 24/10/2017
Completed
Phase - 1
orchid
24.881069216715037,93.9071767330172
24.8919168,93.9115225
1.2833187964272
10
Construction of main gate at Northern side