Progress
 
 
Project Details
DAR-2020-001077
EE/SHD/ Impvt village rd 1km at Happy valley
Improvement of village road 1km, 3 slab culverts at Happy Valley Kangpokpi district
08/03/2019
PWD
Kangpokpi
49.45
0.00
State Plan
In progress
2018-19
24.94624376289243,94.02722167968764
Shingling, WBM, PC, Construction of 1m span RCC slab culvert, Pucca Drain 900mm pipe culvert
Progress Update : 28/11/2020
In progress
2018-19
Sadarhills
24.94624376289243,94.02722167968764
24.9461461,94.0278938
0.068625135552567
0
Shingling, WBM, P.C. 900 mm pipe, pucca drain, 1 m span RCC slab culvert

Progress Update : 28/11/2020
In progress
2018-19
Sadarhills
24.94624376289243,94.02722167968764
24.9459018,94.027659
0.058219942040162
0
Shingling, WBM, P.C. 900 mm pipe, pucca drain, 1 m span RCC slab culvert