DAR-2020-001072
EE/SHD/Impvt. road from K. Tuikon to K/Geljan
Impvt. of road from Kangchup Tuikon to K/Geljang
16/03/2020
PWD
Kangpokpi
60.00
50
State Plan
100%
2019-20
24.86923329935177,93.80595016479506
Kutcha Drain, formation cutting, shingling, WBM, PC. Const. of 1m span RCC Slab Culvert 1 no. Const. of 2m span RCC Slab Culvert. Pucca drain const.
Progress Update : 18/08/2022
100%
2019-20
Sadarhills
24.86923329935177,93.80595016479506
24.8659549,93.8047703
0.38346396433513
50
Completed BT Surface

Progress Update : 18/08/2022
100%
2019-20
Sadarhills
24.86923329935177,93.80595016479506
24.8669184,93.80526633
0.26647691861249
50
Completed - RCC Slab Culvert

Progress Update : 18/08/2022
100%
2019-20
Sadarhills
24.86923329935177,93.80595016479506
24.86680269,93.80519532
0.28078149567542
50
Pucca Drain : Completed

Progress Update : 04/05/2021
100%
2019-20
Sadarhills
24.86923329935177,93.80595016479506
24.8692214,93.8055252
0.042890414249512
50
Hill cutting in formation widening - Completed

Progress Update : 04/05/2021
100%
2019-20
Sadarhills
24.86923329935177,93.80595016479506
24.8690774,93.8059979
0.017990813622837
50
Hill cutting in widening of formation - completed

Progress Update : 04/05/2021
In progress
2019-20
Sadarhills
24.86923329935177,93.80595016479506
24.8691182,93.8061768
0.0262008816308
0
Shingling, wbm, pc, constr. of 1 m span and 2 m span RCC slab culvert, earth work

Progress Update : 04/05/2021
In progress
2019-20
Sadarhills
24.86923329935177,93.80595016479506
24.8692578,93.806022
0.0077413668013912
0
Shingling, wbm, pc, constr. of 1 m span and 2 m span RCC slab culvert, earth work

Progress Update : 04/05/2021
In progress
2019-20
Sadarhills
24.86923329935177,93.80595016479506
24.8666181,93.8048746
0.31036688820375
0
Shingling, wbm, pc, constr. of 1 m span and 2 m span RCC slab culvert, earth work

Progress Update : 04/05/2021
100%
2019-20
Sadarhills
24.86923329935177,93.80595016479506
24.8663979,93.8046064
0.34317557572361
50
BT Surface - Completed

Progress Update : 30/11/2020
In progress
2019-20
Sadarhills
24.86923329935177,93.80595016479506
24.8667329,93.8050526
0.29239158153324
0
Earth work in formation cutting, shrinking, wbm, PC, construction of 1 m & 2 m span RCC Slab culvert, pucca drain