Progress
 
 
Project Details
DAR-2020-000996
TPL-CSC-TOLLEN
Construction of Community Sanitary Complex at TOLLEN
20/11/2019
PHED
Tengnoupal
200000.00
120000
Completed
First
24.608459515229335,94.09479188919082
CSC TOLLEN
Progress Update : 27/11/2020
Completed
First
solo
24.608459515229335,94.09479188919082
23.992563333333,93.559328333333
87.373281773506
120000
CSC

Progress Update : 25/11/2020
Completed
Phase 1
tengnoupal
24.608459515229335,94.09479188919082
24.6096582,94.0940265
0.15411208121853
120000
CSC AT TOLLEN