DAR-2020-000880
7/1/2020- PHE(10B)(Satu/Ghetao-II JJM)
Aug. of Water Supply scheme at Satu/Ghetao-II
15/07/2020
PHED
Noney
50.00
0.00
Central Sector
Ongoing
Phase 1
24.6523037,93.5676421
1. Construction of Intake Arrangement. 2. Construction of Settling Tank - 10,000 Ltr. Capacity. 3. Construction of Zonal Reservoir - 10,000 Ltr. capacity. 4. Construction of Distribution Tank - 3000 Ltr. Capacity. 5. Construction of Fencing in Treatment Site. 6. Construction of Trace Path and approach road. 7. Mechanical Transportation of G.I. Pipe. 8. Laying and Fixing of G.I. Pipe.
Progress Update : 26/11/2020
Ongoing
Phase 1
eenoneydo
24.6523037,93.5676421
24.6726005,93.5229339
5.0499619238097
0
Settling Tank

Progress Update : 26/11/2020
Ongoing
Phase1
eenoneydo
24.6523037,93.5676421
24.6748281,93.5237927
5.0896485164181
0
Zonal Reservoir