Progress
 
 
Project Details
DAR-2020-000813
JJM Senapati/Robve Solephe
Augmentation of Robve Solephe W/S scheme
15/07/2020
PHED
Senapati
115.00
21.00
Central Sector
Ongoing scheme
phase 1
25.498043741944088,94.19978340351562
Progress Update : 20/05/2022
Ongoing scheme
phase 1
kameispt
25.498043741944088,94.19978340351562
25.4901783,94.1636941
3.7261175924594
0
Settling tank

Progress Update : 12/11/2020
Ongoing
Phase 1
Lohrii
25.498043741944088,94.19978340351562
25.5316366,94.1998641
3.7351844535286
0
Service Reservior

Progress Update : 12/11/2020
Ongoing
Phase 1
Lohrii
25.498043741944088,94.19978340351562
25.4946657,94.199842
0.37564909352038
0
Service Reservior

Progress Update : 12/11/2020
Ongoing
Phase 1
Lohrii
25.498043741944088,94.19978340351562
25.49466571,94.199842
0.37564797798102
0
S.S.F.