Progress
 
 
Project Details
DAR-2020-000573
SS/19-KakchingKhullenUPS-KAK
Strengthening of School under Samagra Shiksha for the year 2019-20 of Kakching Khullen Upper Primary School, Kakching District, Manipur.
16/12/2019
Education (S)
Kakching
37.36
29.17
Samagra Shiksha
Completed
nill
24.493438950884514,93.99350113053285
Strengthening of School under Samagra Shiksha for the year 2019-20 of Kakching Khullen Upper Primary School, Kakching District, Manipur. (SH: Construction of 2(two) ACRs) (Providing of IEI)
Progress Update : 10/09/2022
Completed
nill
so7.eew
24.493438950884514,93.99350113053285
24.49347531,93.9936061
0.011364758796592
0
Front View

Progress Update : 10/09/2022
Completed IEI
Front view
so7.eew
24.493438950884514,93.99350113053285
24.4926498,93.9947799
0.15633684876919
0
Interior view (Providing of IEI)

Progress Update : 10/09/2022
Completed
nill
so7.eew
24.493438950884514,93.99350113053285
24.4926399,93.9948871
0.16601275971929
0
Interior View

Progress Update : 10/09/2022
Completed
nill
so7.eew
24.493438950884514,93.99350113053285
24.49341886,93.99348434
0.0028064837979574
0
Interior View

Progress Update : 10/09/2022
Completed IEI
Front view
so7.eew
24.493438950884514,93.99350113053285
24.49406422,93.99326651
0.073464794149065
0
Electric Fuse

Progress Update : 10/09/2022
Completed
nill
so7.eew
24.493438950884514,93.99350113053285
24.49332588,93.99358046
0.01491591079511
0
Verandah View

Progress Update : 10/09/2022
Completed IEI
Front view
so7.eew
24.493438950884514,93.99350113053285
24.49335009,93.99337463
0.016169465253465
0
Front view (Providing of IEI)

Progress Update : 10/06/2022
Under Construction
nill
so7.eew
24.493438950884514,93.99350113053285
24.4926245,93.9949172
0.16950200277495
0
Verandah View

Progress Update : 10/06/2022
Under Construction
nill
so7.eew
24.493438950884514,93.99350113053285
24.4920146,93.9886733
0.5135306803947
0
Interior View

Progress Update : 10/06/2022
Under Construction
nill
so7.eew
24.493438950884514,93.99350113053285
24.4933578,93.9946994
0.12158043689069
0
Interior View

Progress Update : 10/06/2022
Under Construction
nill
so7.eew
24.493438950884514,93.99350113053285
24.4939172,93.9885725
0.501522185203
0
Front view

Progress Update : 02/10/2020
Work in progress
Nill
kh1.eew-mn
24.493438950884514,93.99350113053285
24.493626,93.9937526
0.032863039075424
0
Back view

Progress Update : 02/10/2020
Work in progress
Nill
kh1.eew-mn
24.493438950884514,93.99350113053285
24.4925913,93.9956563
0.23756435710299
0
Front view

Progress Update : 02/10/2020
Work in progress
Nill
kh1.eew-mn
24.493438950884514,93.99350113053285
24.4925913,93.9956563
0.23756435710299
0
Front view