Progress
 
 
Project Details
DAR-2020-000513
EVM-KPI
Construction of Kangpokpi DEO/DC EVMs Strong Room
05/11/2019
Manipur Police Housing Corporation Ltd.
Kangpokpi
305.34
305.34
Manipur Police Housing Corporation Ltd.
State Plan
100% Completed
Single
25.1518638,93.9672845
It is an R.C.C. (G+1) framed structure Building meant for storage of EVM & VVPAT of 3 (three) Assembly Constituencies viz, Saikhul, Kangpokpi and Saitu of Kangpokpi District, . The building has also rooms for First Level Checking (FLC), FLC hall, Security Room, Training room and Extra EVM & VVPAT Strong Rooms.
Progress Update : 25/07/2022
100% Completed
Single
aesptmphc
25.1518638,93.9672845
25.1514933,93.9669583
0.052678002441048
305.34
Completed

Progress Update : 25/07/2022
100% Completed
Single
aesptmphc
25.1518638,93.9672845
25.153563,93.968234
0.21172677308078
305.34
Completed

Progress Update : 25/07/2022
100% Completed
Single
aesptmphc
25.1518638,93.9672845
25.1464103,93.9684202
0.61705237033529
305.34
Completed

Progress Update : 29/12/2021
100 % Completed
Single
aesptmphc
25.1518638,93.9672845
25.151866,93.9664157
0.087442540188197
305.34
Completed

Progress Update : 07/12/2021
100% Completed
Single
aesptmphc
25.1518638,93.9672845
25.1510074,93.9669589
0.1007040116426
305.34
Completed

Progress Update : 22/06/2021
70 percent completed
Single
aesptmphc
25.1518638,93.9672845
25.1517268,93.9677404
0.048347616213342
107
Construction of Kangpokpi DC/DEO EVM and VVPAT warehouse, northern side

Progress Update : 22/06/2021
70 percent completed
Single
aesptmphc
25.1518638,93.9672845
25.151618333333,93.966998333333
0.03967968270296
107
Construction of Kangpokpi DC/DEO EVM and VVPAT warehouse, northern side

Progress Update : 22/06/2021
70 percent completed
Single
aesptmphc
25.1518638,93.9672845
25.1517292,93.9670535
0.027650113269664
107
Construction of Kangpokpi DC/DEO EVM and VVPAT warehouse, northern side

Progress Update : 22/06/2021
70 percent completed
Single
aesptmphc
25.1518638,93.9672845
25.1517268,93.9677404
0.048347616213342
107
Construction of Kangpokpi DC/DEO EVM and VVPAT warehouse, Front side

Progress Update : 22/06/2021
70 percent completed
Single
aesptmphc
25.1518638,93.9672845
25.1517268,93.9677404
0.048347616213342
107
Construction of Kangpokpi DC/DEO EVM and VVPAT warehouse, Front side

Progress Update : 30/01/2021
45 percent completed
Single
aesptmphc
25.1518638,93.9672845
25.14735,93.965365
0.5377877164477
100
Construction of Kangpokpi DC/DEO EVM and VVPAT strong room

Progress Update : 30/01/2021
45 percent completed
Single
aesptmphc
25.1518638,93.9672845
25.1508433,93.96589
0.18048309284602
100
Construction of Kangpokpi DC/DEO EVM and VVPAT strong room back side

Progress Update : 30/01/2021
45 percent completed
Single
aesptmphc
25.1518638,93.9672845
25.1515783,93.9667633
0.061314670505403
100
Construction of Kangpokpi DC/DEO EVM and VVPAT strong room back side

Progress Update : 29/09/2020
5 percent completed
Single
aesptmphc
25.1518638,93.9672845
25.1425664,93.9644088
1.0735293208973
0
Construction of Kangpokpi DC/DEO EVM and VVPAT warehouse,erection of columns in progress

Progress Update : 29/09/2020
5 percent completed
Single
aesptmphc
25.1518638,93.9672845
25.1484177,93.9669589
0.38456924028829
0
Construction of Kangpokpi DC/DEO EVM and VVPAT warehouse

Progress Update : 29/09/2020
5 percent completed
Single
aesptmphc
25.1518638,93.9672845
25.1538649,93.9707843
0.41663072016716
0
Construction of Kangpokpi DC/DEO EVM and VVPAT warehouse