Progress
 
 
Project Details
DAR-2020-000509
SS/19-KumbiSandhongUPS-BPR
Strengthening of School under Samagra Shiksha 2019-20 at Kumbi Sandhong UPS, Bishnupur District, Manipur.
16/12/2019
Education (S)
Bishnupur
29.26
21.54
Samagra Shiksha
completed
nil
24.435529801182565,93.8042564999359
Strengthening of School under Samagra Shiksha 2019-20 at Kumbi Sandhong UPS, Bishnupur District, Manipur. (SH Construction of 2 (two) ACR)
Progress Update : 02/08/2024
completed
nil
sur1.eew-mn
24.435529801182565,93.8042564999359
24.4356441,93.8043745
0.017441180601886
0
front view IEI

Progress Update : 02/08/2024
completed
nil
sur1.eew-mn
24.435529801182565,93.8042564999359
24.4348066,93.8023419
0.20983477600497
0
main switch iei

Progress Update : 02/08/2024
completed
nil
sur1.eew-mn
24.435529801182565,93.8042564999359
24.4356129,93.8043441
0.012806855724864
0
room IEI

Progress Update : 02/08/2024
completed
nil
sur1.eew-mn
24.435529801182565,93.8042564999359
24.4340559,93.800127
0.44900788493013
0
room IEI

Progress Update : 11/09/2022
Inprogess
Nil
sur1.eew-mn
24.435529801182565,93.8042564999359
24.4355956,93.804642
0.039704090038459
0
2ACR (room)

Progress Update : 11/09/2022
Inprogess
Nil
sur1.eew-mn
24.435529801182565,93.8042564999359
24.4356542,93.8042991
0.014488681267334
0
2ACR (side view)

Progress Update : 11/09/2022
Inprogess
Nil
sur1.eew-mn
24.435529801182565,93.8042564999359
24.4356675,93.8043117
0.016298807493236
0
2ACR (front view)

Progress Update : 23/05/2022
Inprogess
Nil
sur1.eew-mn
24.435529801182565,93.8042564999359
24.4357574,93.8043187
0.026078320065337
0
Side view

Progress Update : 23/05/2022
Inprogess
Nil
sur1.eew-mn
24.435529801182565,93.8042564999359
24.4358807,93.8043231
0.039594650653759
0
Front view

Progress Update : 06/09/2020
Work in progress
Nill
kh1.eew-mn
24.435529801182565,93.8042564999359
24.4359345,93.8059131
0.17362968160071
0
Back view

Progress Update : 06/09/2020
Work in progress
Nill
kh1.eew-mn
24.435529801182565,93.8042564999359
24.4359345,93.8059131
0.17362968160071
0
Side view

Progress Update : 06/09/2020
Work in progress
Nill
kh1.eew-mn
24.435529801182565,93.8042564999359
24.433718,93.8055953
0.24279877529612
0
Front view