Progress
 
 
Project Details
DAR-2020-000498
WRD-FCW-127
Re-sectioning of Keirou Stream from RD 0.00 m to RD 2000.00 m
15/06/2020
Water Resources Department (WRD)
Bishnupur
14.00
0.00
State Plan
Completed
Final
24.46935278,93.80333333
Progress Update : 02/09/2020
Completed
Final
FCD-4
24.46935278,93.80333333
24.4682066,93.7903446
1.320666052668
0
Re-sectioning of Keirou Stream from RD.0.00m to RD.2000.00 m

Progress Update : 02/09/2020
Completed
Final
FCD-4
24.46935278,93.80333333
24.4790577,93.8011467
1.1015413721486
0
Re-sectioning of Keirou Stream from RD.0.00m to RD.2000.00 m

Progress Update : 02/09/2020
Completed
Final
FCD-4
24.46935278,93.80333333
24.4790577,93.8011467
1.1015413721486
0
Re-sectioning of Keirou Stream from RD.0.00m to RD.2000.00 m