Progress
 
 
Project Details
DAR-2020-000494
EVMIW
Construction of Imphal West DEO/DC EVMs Strong Room.
05/11/2019
Manipur Police Housing Corporation Ltd.
Imphal-West
473.64
403
Manipur Police Housing Corporation Ltd.
State Plan
85% Completed.
Single
24.8117651,93.9125508
It is an R.C.C. framed structure (G+2) Building meant for storage of EVMs & VVPAT of 13 ( thirteen) Assembly Constituencies of Imphal West District. The building has also rooms for FLC, FLC hall, Training room, Security Room, Extra room for Reserve EVM & VVPAT etc.
Progress Update : 18/07/2022
85% Completed.
Single
ee1mphc2017
24.8117651,93.9125508
24.8115124,93.9134331
0.093374688858037
403
Finishing items in progress

Progress Update : 18/07/2022
85% Completed.
Single
ee1mphc2017
24.8117651,93.9125508
24.8115124,93.9134331
0.093374688858037
403
Finishing items in progress

Progress Update : 18/07/2022
85% Completed.
Single
ee1mphc2017
24.8117651,93.9125508
24.8115124,93.9134331
0.093374688858037
403
Finishing items in progress

Progress Update : 06/08/2021
45%
Single
ee1mphc2017
24.8117651,93.9125508
24.8108775,93.9122995
0.10189870984576
135
Casting of ground floor column is completed. Shuttering of beam & slab in progress.

Progress Update : 06/08/2021
45%
Single
ee1mphc2017
24.8117651,93.9125508
24.8109213,93.9122588
0.098341364208376
135
Casting of ground floor column is completed. Shuttering of beam & slab in progress.

Progress Update : 22/06/2021
45% completed
Single
ee1mphc2017
24.8117651,93.9125508
24.8108648,93.9126393
0.10050165397404
135
Casting of ground floor column completed, shuttering of beam and slab in progress.

Progress Update : 22/06/2021
45% completed
Single
ee1mphc2017
24.8117651,93.9125508
24.8106914,93.9124016
0.12033015889436
135
Casting of ground floor column completed, shuttering of beam and slab in progress.

Progress Update : 22/06/2021
45% completed
Single
ee1mphc2017
24.8117651,93.9125508
24.8109881,93.9126563
0.087047908289625
135
Casting of ground floor column completed, shuttering of beam and slab in progress.

Progress Update : 20/03/2021
35% Completed
Single
ee1mphc2017
24.8117651,93.9125508
24.8114853,93.9126985
0.034497884950972
140
Casting of Ground floor column completed.

Progress Update : 20/03/2021
35% Completed.
Single
ee1mphc2017
24.8117651,93.9125508
24.810888,93.912564
0.097533460620989
140
Casting of Ground floor column completed.

Progress Update : 20/03/2021
35% Completed
Single
ee1mphc2017
24.8117651,93.9125508
24.8109081,93.9131147
0.1109913603043
140
Casting of Ground floor column completed.

Progress Update : 30/01/2021
30% Completed.
Single
ee1mphc2017
24.8117651,93.9125508
24.8113157,93.9127495
0.053842547937136
120
Brick work upto plinth beam is in progress.

Progress Update : 30/01/2021
3o% completed
Single
ee1mphc2017
24.8117651,93.9125508
24.8113167,93.91275
0.053758292883043
120
Brick work upto plinth beam is in progress.

Progress Update : 30/01/2021
3o% completed
Single
ee1mphc2017
24.8117651,93.9125508
24.8109424,93.9132376
0.11477160657169
120
Brick work upto plinth beam is in progress.

Progress Update : 26/11/2020
Pile foundation completed
Phase 1
ee1mphc2017
24.8117651,93.9125508
24.8115041,93.9137516
0.12461801826339
90
Construction of EVM Imphal West (DC)

Progress Update : 02/10/2020
Pile foundation in progress
Phase-1
ee1mphc2017
24.8117651,93.9125508
24.8114699,93.9128174
0.042442212127165
90
RCC framed structure (G+2) building

Progress Update : 02/10/2020
Pile foundation in progress
Phase-1
ee1mphc2017
24.8117651,93.9125508
24.8117651,93.9125508
0
0
RCC framed structure (G+2) building