Progress
 
 
Project Details
DAR-2020-000366
SS/19-INAMemorialHS-CCpur
Strengthening of School under RMSA 2019-20 of INA Memorial High School, (Govt.), Churachandpur District
31/10/2019
Education (S)
Churachandpur
105.33
67.58
Samagra Shiksha
completed
nil
24.4479517388537,93.72972493869248
Strengthening of School under RMSA 2019-20 of INA Memorial High School, (Govt.), Churachandpur District (Sh: Construction of 5 (five) Room Residential Quarter) Change to:- Construction of 5(five) ACR vide No. 3-15/SPD/RMSA/SIS/2009(Pt.3) Dt: 31st Oct, 2019 (Sh: Const. of 2(two) ACR)
Progress Update : 22/08/2024
completed
nil
sur1.eew-mn
24.4479517388537,93.72972493869248
24.4479508,93.7297628
0.0038350135278192
0
room 2acr

Progress Update : 22/08/2024
completed
nil
sur1.eew-mn
24.4479517388537,93.72972493869248
24.4480915,93.7300956
0.040609498049194
0
room 2acr

Progress Update : 22/08/2024
completed
nil
sur1.eew-mn
24.4479517388537,93.72972493869248
24.4479819,93.7298606
0.014135437607123
0
verandah 2acr

Progress Update : 22/08/2024
completed
nil
sur1.eew-mn
24.4479517388537,93.72972493869248
24.4480292,93.7294578
0.028378414185002
0
front view 2acr

Progress Update : 28/11/2022
Inprogess
Nil
sur1.eew-mn
24.4479517388537,93.72972493869248
24.44809287,93.72959582
0.020422245760531
0
front view

Progress Update : 28/11/2022
Inprogess
Nil
sur1.eew-mn
24.4479517388537,93.72972493869248
24.4481737,93.72940473
0.04073800523327
0
Room

Progress Update : 28/11/2022
Inprogess
Nil
sur1.eew-mn
24.4479517388537,93.72972493869248
24.44817463,93.72939695
0.041429189091346
0
Room

Progress Update : 28/11/2022
Inprogess
Nil
sur1.eew-mn
24.4479517388537,93.72972493869248
24.44826852,93.72952322
0.040712778952617
0
Verandah

Progress Update : 28/09/2022
In progress
Nil
so5.eew
24.4479517388537,93.72972493869248
24.44832,93.7304451
0.083607839333217
0
2 acr inside

Progress Update : 28/09/2022
In progress
Nil
so5.eew
24.4479517388537,93.72972493869248
24.4483932,93.7304792
0.090764402873369
0
2 acr inside

Progress Update : 28/09/2022
In progress
Nil
so5.eew
24.4479517388537,93.72972493869248
24.4474644,93.7297046
0.05422614174854
0
2 acr verandah

Progress Update : 28/09/2022
In progress
Nil
so5.eew
24.4479517388537,93.72972493869248
24.4479773,93.729582
0.014744548655558
0
2 acr front

Progress Update : 11/06/2022
In Progress
Nil
so4.eew-mn
24.4479517388537,93.72972493869248
24.44819487,93.72996599
0.036416299332961
0
Verandah1

Progress Update : 11/06/2022
In Progress
Nil
so4.eew-mn
24.4479517388537,93.72972493869248
24.4485845,93.7293873
0.078217737474965
0
Inside2

Progress Update : 11/06/2022
In Progress
Nil
so4.eew-mn
24.4479517388537,93.72972493869248
24.4485845,93.7293873
0.078217737474965
0
Inside1

Progress Update : 11/06/2022
In Progress
Nil
so4.eew-mn
24.4479517388537,93.72972493869248
24.44808992,93.72926521
0.04900448995463
0
Front

Progress Update : 16/12/2021
In progress
Nil
so4.eew-mn
24.4479517388537,93.72972493869248
24.448016,93.7294383
0.029880569018601
0
Side view

Progress Update : 16/12/2021
In progress
Nil
so4.eew-mn
24.4479517388537,93.72972493869248
24.448016,93.7294383
0.029880569018601
0
Inside room view

Progress Update : 16/12/2021
In progress
Nil
so4.eew-mn
24.4479517388537,93.72972493869248
24.448016,93.7294383
0.029880569018601
0
Verandah view

Progress Update : 16/12/2021
In progress
Nil
so4.eew-mn
24.4479517388537,93.72972493869248
24.448016,93.7294383
0.029880569018601
0
Front view

Progress Update : 28/04/2020
Work in progress
Nil
sur1.eew-mn
24.4479517388537,93.72972493869248
24.4484367,93.7292183
0.074414249325568
0
Side view

Progress Update : 28/04/2020
Work in progress
Nil
sur1.eew-mn
24.4479517388537,93.72972493869248
24.4484367,93.7292183
0.074414249325568
0
Back view

Progress Update : 28/04/2020
Work in progress
Nil
sur1.eew-mn
24.4479517388537,93.72972493869248
24.4480033,93.729505
0.022988530455694
0
Side view

Progress Update : 28/04/2020
Work in progress
Nil
sur1.eew-mn
24.4479517388537,93.72972493869248
24.4490099,93.7310597
0.17915403325182
0
Front view