Progress
 
 
Project Details
DAR-2020-000304
MSPDCL-CIVILWORK-045
Construction of Sub-divisional office building at Waikhong, (Sugnu Sub-Division) MSPDCL.
2019-03-08
POWER (MSPDCL)
Sugnu
57.41
7.77
State Plan
Completed
NA
24.4133506,93.9281310
Construction of Sub-divisional office building at Waikhong, (Sugnu Sub-Division) MSPDCL.
Progress Update : 2020-06-09
Completed
NA
Hari
24.4133506,93.9281310
24.41361,93.928676666667
0.062323235627731
Approved
2020-06-11 06:53:24
CORPORATEAP2
0
Construction of Sub Divisional Office Building at Waikhong (Sugnu Sub Division)

Progress Update : 2020-06-09
Completed
NA
Hari
24.4133506,93.9281310
24.4095196,93.9242461
0.57979939824122
Approved
2020-06-11 06:54:48
CORPORATEAP2
0
Construction of Sub Divisional Office Building at Waikhong (Sugnu Sub Division)

Progress Update : 2020-06-09
Completed
NA
Hari
24.4133506,93.9281310
24.4095196,93.9242461
0.57979939824122
Approved
2020-06-11 06:58:10
CORPORATEAP2
0
Construction of Sub Divisional Office Building at Waikhong (Sugnu Sub Division)

Progress Update : 2020-06-09
Completed
NA
Hari
24.4133506,93.9281310
24.4095196,93.9242461
0.57979939824122
Approved
2020-06-11 06:58:36
CORPORATEAP2
0
Construction of Sub Divisional Office Building at Waikhong (Sugnu Sub Division)

Progress Update : 2020-06-09
Completed
NA
Hari
24.4133506,93.9281310
24.4095196,93.9242461
0.57979939824122
Approved
2020-06-11 07:03:07
CORPORATEAP2
0
Construction of Sub Divisional Office Building at Waikhong (Sugnu Sub Division)

Progress Update : 2020-06-09
Completed
NA
Hari
24.4133506,93.9281310
24.413271666667,93.928958333333
0.084224264689718
Approved
2020-06-11 07:03:24
CORPORATEAP2
0
Construction of Sub Divisional Office Building at Wakhong (Sugnu SD)

Progress Update : 2020-06-09
Completed
NA
Hari
24.4133506,93.9281310
24.4132328,93.9289799
0.086941624291975
Approved
2020-06-11 07:03:43
CORPORATEAP2
0
Construction of Sub Divisional Office Building at Wakhong (Sugnu SD)

Foundation & Inauguration
-
-
-

-
-
-