Progress
 
 
Project Details
DAR-2020-000302
MSPDCL-CIVILWORK-043
Construction of boundary fencing for the new office building at Senapati, MSPDCL.
08/03/2019
POWER (MSPDCL)
Senapati
47.99
0.00
State Plan
Ongoing
Na
25.271652,94.023015
Construction of boundary fencing for the new office building at Senapati, MSPDCL.
Progress Update : 01/07/2020
Ongoing
Na
Rajesh
25.271652,94.023015
25.2711481,94.0246128
0.17014563834211
0
Construction of boundary fencing for the new office building at Senapati, MSPDCL

Progress Update : 01/07/2020
Ongoing
Na
Rajesh
25.271652,94.023015
25.2708592,94.0239806
0.13113727819307
0
Construction of boundary fencing for the new office building at Senapati, MSPDCL

Progress Update : 01/07/2020
Ongoing
Na
Rajesh
25.271652,94.023015
25.2711454,94.0246165
0.17059585827475
0
Construction of boundary fencing for the new office building at Senapati, MSPDCL

Progress Update : 01/07/2020
Ongoing
Na
Rajesh
25.271652,94.023015
25.2696779,94.0240483
0.24284683642212
0
Construction of boundary fencing for the new office building at Senapati, MSPDCL

Progress Update : 01/07/2020
Ongoing
Na
Rajesh
25.271652,94.023015
25.2686217,94.0221357
0.34834454841358
0
Construction of boundary fencing for the new office building at Senapati, MSPDCL