Progress
 
 
Project Details
DAR-2020-000238
SS/19-GhariUPS-IW
Strengthening of School under Samagra Shiksha for the year 2019-20 of Ghari UPS, Imphal West District, Manipur.
16/12/2019
Education (S)
Imphal-West
47.06
44.09
Samagra Shiksha
Completed
Nil
24.777199282296497,93.90859894113922
Strengthening of School under Samagra Shiksha for the year 2019-20 of Ghari UPS, Imphal West District, Manipur. (SH: Construction of 3 ACR) (Providing of I.E.I)
Progress Update : 07/09/2022
Completed
Nil
so5.eew
24.777199282296497,93.90859894113922
24.7769917,93.9087237
0.026293927387584
0
Inside room

Progress Update : 07/09/2022
Completed
Nil
so5.eew
24.777199282296497,93.90859894113922
24.7771343,93.9081506
0.045834833573133
0
Inside room

Progress Update : 09/06/2022
Completed
Nill
so4.eew-mn
24.777199282296497,93.90859894113922
24.7771304,93.9082309
0.037936320165797
0
IEI connection

Progress Update : 09/06/2022
Completed
Nill
so4.eew-mn
24.777199282296497,93.90859894113922
24.7770252,93.9087057
0.022154481486663
0
IEI classroom1 fan and light

Progress Update : 09/06/2022
Completed
Nill
so4.eew-mn
24.777199282296497,93.90859894113922
24.7783549,93.9084093
0.12991103123012
0
IEI classroom fan and light

Progress Update : 09/06/2022
Completed
Nill
so4.eew-mn
24.777199282296497,93.90859894113922
24.7782906,93.9083338
0.12426030127496
0
IEI verandah light

Progress Update : 24/10/2021
In progress
Nil
so5.eew
24.777199282296497,93.90859894113922
24.7770906,93.9082069
0.041381850572438
0
Inside view

Progress Update : 24/10/2021
In progress
Nil
so5.eew
24.777199282296497,93.90859894113922
24.7772108,93.9081265
0.047711924518557
0
Verandah

Progress Update : 24/10/2021
In progress
Nil
so5.eew
24.777199282296497,93.90859894113922
24.77813,93.9084643
0.10437498916703
0
Front view

Progress Update : 24/10/2021
In progress
Nil
so5.eew
24.777199282296497,93.90859894113922
24.77813,93.9084643
0.10437498916703
0
Front view

Progress Update : 06/03/2020
Work in progress
Nill
kh1.eew-mn
24.777199282296497,93.90859894113922
24.7786253,93.9105673
0.25421912593535
0
Front view

Progress Update : 06/03/2020
Work in progress
nill
kh1.eew-mn
24.777199282296497,93.90859894113922
24.7786336,93.9102488
0.23059938726358
0
Side view