Progress
 
 
Project Details
DAR-2020-000183
SS/19-PhundreiHS(RQ)-TBL
Construction of 5(five) Residential Quarter at Phundrei High School, Thoubal
31/10/2019
Education (S)
Thoubal
83.14
74.86
Samagra Shiksha
Completed
Nil
24.553427123720766,94.050749172422
Construction of 5(five) Residential Quarter at Phundrei High School, Thoubal (Sh: Providing of I.E.I) (Sh: Land Development i/c Providing W.S. & S.I)
Progress Update : 19/03/2024
Completed
Nil
sur1.eew-mn
24.553427123720766,94.050749172422
24.5530736,94.0486287
0.21802732846261
0
Senetary

Progress Update : 19/03/2024
Completed
Nil
sur1.eew-mn
24.553427123720766,94.050749172422
24.5530736,94.0486287
0.21802732846261
0
Senetary

Progress Update : 19/03/2024
Completed
Nil
sur1.eew-mn
24.553427123720766,94.050749172422
24.5534279,94.0511062
0.036108011204316
0
Land development

Progress Update : 20/11/2023
Completed
Nil
sur1.eew-mn
24.553427123720766,94.050749172422
24.5535087,94.050772
0.0093601892875736
0
Iei(room)

Progress Update : 20/11/2023
Completed
Nil
sur1.eew-mn
24.553427123720766,94.050749172422
24.5535029,94.0507638
0.008554833831952
0
Iei(room)

Progress Update : 22/11/2022
Completed
Nil
so5.eew
24.553427123720766,94.050749172422
24.55336571,94.05086246
0.013338021013189
0
Inside view quarter

Progress Update : 22/11/2022
Completed
Nil
so5.eew
24.553427123720766,94.050749172422
24.55325835,94.05087844
0.022870623654617
0
Inside view quater (Kitchen)

Progress Update : 22/11/2022
Completed
Nil
so5.eew
24.553427123720766,94.050749172422
24.55342527,94.05091776
0.017051366811295
0
Front view quarter UC

Progress Update : 22/11/2022
Completed
Nil
so5.eew
24.553427123720766,94.050749172422
24.55347148,94.05112754
0.038582773322479
0
Front view quater

Progress Update : 31/12/2021
In progress
Nil
so5.eew
24.553427123720766,94.050749172422
24.5534349,94.0506428
0.010792918530231
0
Septic tank

Progress Update : 31/12/2021
In progress
Nil
so5.eew
24.553427123720766,94.050749172422
24.55344,94.0509683
0.022207501910909
0
Side view

Progress Update : 31/12/2021
In progress
Nil
so5.eew
24.553427123720766,94.050749172422
24.55344,94.0509683
0.022207501910909
0
Inside view

Progress Update : 31/12/2021
In progress
Nil
so5.eew
24.553427123720766,94.050749172422
24.5534273,94.0510575
0.031182830417078
0
Front view

Progress Update : 23/02/2020
Work in progress
Nill
kh1.eew-mn
24.553427123720766,94.050749172422
24.549824,94.0454361
0.67025753425853
0
Front

Progress Update : 23/02/2020
Work in progress
Nill
kh1.eew-mn
24.553427123720766,94.050749172422
24.5839951,94.0700244
3.9180815064451
0
Front

Progress Update : 23/02/2020
Work in progress
Nill
kh1.eew-mn
24.553427123720766,94.050749172422
24.5532463,94.0510205
0.034018199136251
0
Back view

Progress Update : 23/02/2020
Work in progress
Nill
kh1.eew-mn
24.553427123720766,94.050749172422
24.5590988,94.0316937
2.0276943780193
0
Front

Progress Update : 23/02/2020
Work in progress
Nill
kh1.eew-mn
24.553427123720766,94.050749172422
24.5590988,94.0316937
2.0276943780193
0
Front