Progress
 
 
Project Details
DAR-2019-000578
ND/ROAD/Taosang-Lubanglong/8
Construction of road from Taosang to Lubanglong.
04/03/2019
PWD
Noney
75.00
68.5
State Plan
100%
2nd & Final Phase
24.734812396240457,93.5591440200808
Jungle clearance, surface dressing, Earth Work & Kutcha line drain
Progress Update : 29/04/2020
100%
2nd & Final Phase
7085631665
24.734812396240457,93.5591440200808
24.8626732,93.6178491
15.402219785078
68.5

Progress Update : 29/04/2020
100% completed
2nd & Final Phase
7085631665
24.734812396240457,93.5591440200808
24.7377162,93.5615787
0.40583199308776
68.5
Kutcha Line Drain

Progress Update : 14/03/2020
100% completed
final
7085631665
24.734812396240457,93.5591440200808
24.735368,93.5589926
0.063641692033247
68.5
Clearance jungle, surface dressing, hill cutting & kutcha line drain

Progress Update : 14/03/2020
80%
1st phase
7085631665
24.734812396240457,93.5591440200808
24.735368,93.5589926
0.063641692033247
0
Clearance jungle, surface dressing, hill cutting & kutcha line drain

Progress Update : 14/03/2020
80%
1st phase
7085631665
24.734812396240457,93.5591440200808
24.735368,93.5589926
0.063641692033247
0
Clearance jungle, surface dressing, hill cutting & kutcha line drain

Progress Update : 14/03/2020
80%
1st phase
7085631665
24.734812396240457,93.5591440200808
24.735368,93.5589926
0.063641692033247
0
Clearance jungle, surface dressing, hill cutting & kitchen line drain

Progress Update : 14/03/2020
80%
1st phase
7085631665
24.734812396240457,93.5591440200808
24.735368,93.5589926
0.063641692033247
0
Clearance jungle, surface dressing, hill cutting & kutcha line drain

Progress Update : 14/03/2020
80%
1st phase
7085631665
24.734812396240457,93.5591440200808
24.735368,93.5589926
0.063641692033247
0
Clearance jungle, surface dressing, hill cutting & kitchen line drain

Progress Update : 14/03/2020
80%
1st phase
7085631665
24.734812396240457,93.5591440200808
24.735368,93.5589926
0.063641692033247
0
Clearance jungle, surface dressing, hill cutting & kutcha line drain

Progress Update : 14/03/2020
80%
1st phase
7085631665
24.734812396240457,93.5591440200808
24.735368,93.5589926
0.063641692033247
0
Clearance jungle, surface dressing, hill cutting & kutcha line drain

Progress Update : 14/03/2020
80%
1st phase
7085631665
24.734812396240457,93.5591440200808
24.735368,93.5589926
0.063641692033247
0
Clearance jungle, surface dressing, hill cutting & kutcha line drain

Progress Update : 14/03/2020
80%
1st phase
7085631665
24.734812396240457,93.5591440200808
24.735368,93.5589926
0.063641692033247
0
Clearance jungle, surface dressing, hill cutting & kutcha line drain

Progress Update : 14/03/2020
80%
1st phase
7085631665
24.734812396240457,93.5591440200808
24.735368,93.5589926
0.063641692033247
0
Clearance jungle, surface dressing, hill cutting & kutcha line drain

Progress Update : 14/03/2020
80%
1st phase
7085631665
24.734812396240457,93.5591440200808
24.735368,93.5589926
0.063641692033247
0
Clearance jungle, surface dressing, hill cutting & kutcha line drain

Progress Update : 14/03/2020
80%
1st phase
7085631665
24.734812396240457,93.5591440200808
24.735368,93.5589926
0.063641692033247
0
Clearance jungle, surface dressing, hill cutting & kutcha line drain

Progress Update : 14/03/2020
80%
1st phase
7085631665
24.734812396240457,93.5591440200808
24.735368,93.5589926
0.063641692033247
0
Clearance jungle, surface dressing, hill cutting & kitchen line drain

Progress Update : 14/03/2020
80%
1st phase
7085631665
24.734812396240457,93.5591440200808
24.735368,93.5589926
0.063641692033247
0
Clearance jungle, surface dressing, hill cutting & kutcha line drain

Progress Update : 14/03/2020
80%
1st phase
7085631665
24.734812396240457,93.5591440200808
24.735368,93.5589926
0.063641692033247
0
Clearance jungle, surface dressing, hill cutting & kutcha line drain

Progress Update : 14/03/2020
80%
1st phase
7085631665
24.734812396240457,93.5591440200808
24.735368,93.5589926
0.063641692033247
0
Clearance jungle, surface dressing, hill cutting & kutcha line drain

Progress Update : 14/03/2020
80%
1st phase
7085631665
24.734812396240457,93.5591440200808
24.735368,93.5589926
0.063641692033247
0
Clearance jungle, surface dressing, hill cutting & kutcha line drain

Progress Update : 14/03/2020
80%
1st phase
7085631665
24.734812396240457,93.5591440200808
24.735368,93.5589926
0.063641692033247
0
Clearance jungle, surface dressing, hill cutting & kutcha line drain