DAR-2019-000467
WRD-WB-06
Rejuvenation of Lamphelpat Waterbody(SH - Construction of bridge for motors, pedestrians etc. at Lamphelpat, Imphal West, Manipur)
09/01/2024
Water Resources Department (WRD)
Imphal-West
7450.00
0.00
New Development Bank
Ongoing
Foundation Construction
24.83026,93.91623
Construction of 245 m cable stayed bridge.
Progress Update : 28/02/2025
Ongoing
Foundation Construction
IID
24.83026,93.91623
24.8311833,93.9167183
0.11387418938486
0
Construction of substructure Abutment A1 under Package IV Construction of bridge, Lamphel, Manipur.

Progress Update : 28/02/2025
Ongoing
Pile Reinforcement
IID
24.83026,93.91623
24.8316116,93.9153635
0.17386990262855
0
Reinforcement for pile construction under Package IV Construction of bridge, Lamphel, Manipur.

Progress Update : 28/02/2025
Ongoing
Foundation works
IID
24.83026,93.91623
24.8308989,93.9160505
0.073311912325317
0
Construction of Piles at Pier-II location under Package IV Construction of bridge, Lamphel, Manipur.

Progress Update : 28/02/2025
Ongoing
Foundation works
IID
24.83026,93.91623
24.8302615,93.9162735
0.0043925342516597
0
Construction of substructure Abutment A2 under Package IV Construction of bridge, Lamphel, Manipur.

Progress Update : 21/02/2025
Ongoing
Foundation Work for Abutment A1 and A2
IID
24.83026,93.91623
24.8324167,93.9160317
0.24063599518462
0
Package IV Construction of bridge for motorable and pedestrian - Completion of Group Pile for A1 and A2, Completion of Pile Cap for A1

Progress Update : 21/02/2025
ongoing
Phase -1(Foundation works)
IID
24.83026,93.91623
24.8321285,93.9152862
0.22854695123905
0
Abutment A1 work