Progress
 
 
Project Details
DAR-2019-000459
AKAMPAT/Approach Road and Culvert
Construction of Mini Sports Complex at Akampat SEYO Club Ground, Imphal East, Manipur(SH:Constn of Approach Road and Culvert)
30/06/2018
PWD
Imphal-East
2000.00
97.63
State Plan
65%
III
24.78081101453558,93.94696348014827
Constn. of approach road and culvert, etc.
Progress Update : 28/10/2020
65%
III
7085969655
24.78081101453558,93.94696348014827
24.78025816,93.94674112
0.065441984809638
97.63
Laying of sand gravel, WBM, construction of culvert etc

Progress Update : 28/10/2020
65%
III
7085969655
24.78081101453558,93.94696348014827
24.78031456,93.94671272
0.060728368831911
97.63
Laying of sand gravel, WBM, construction of culvert etc

Progress Update : 28/10/2020
65%
III
7085969655
24.78081101453558,93.94696348014827
24.78041511,93.94774717
0.090536697385186
97.63
Laying of sand gravel, WBM, construction of culvert etc

Progress Update : 17/06/2020
In progress
II
7085969655
24.78081101453558,93.94696348014827
24.77992627,93.94645269
0.11106960383771
223.5
Laying of sand gravel, WBM etc

Progress Update : 16/06/2020
In progress
II
7085969655
24.78081101453558,93.94696348014827
24.7802442,93.94680298
0.065073336650526
223.5
Laying of sand gravel, WBM, Culverts etc

Progress Update : 16/06/2020
In progress
II
7085969655
24.78081101453558,93.94696348014827
24.78161071,93.94596845
0.13415055835448
223.5
Laying of sand gravel, WBM, Culverts etc

Progress Update : 19/03/2020
In progress
II
7085969655
24.78081101453558,93.94696348014827
24.7817754,93.9459243
0.15001140152893
223.5
Laying of sand gravel, construction of culvert etc

Progress Update : 19/03/2020
In progress
II
7085969655
24.78081101453558,93.94696348014827
24.78044496,93.94723116
0.04885521299958
223.5
Laying of sand gravel, construction of culvert etc

Progress Update : 18/03/2020
In progress
Phase-II
7085969655
24.78081101453558,93.94696348014827
24.78152915,93.94596832
0.1283297758821
223.5
Laying of sand gravel for approach road and construction of culvert

Progress Update : 18/03/2020
In progress
Phase-II
7085969655
24.78081101453558,93.94696348014827
24.78027629,93.94673683
0.063706442388119
223.5
Laying of sand gravel for approach road and construction of culvert

Progress Update : 16/09/2019
Ongoing
1
7085969655
24.78081101453558,93.94696348014827
24.780227,93.9484735
0.16569304455557
0
Approach Road

Progress Update : 12/09/2019
Ongoing
1
7085969655
24.78081101453558,93.94696348014827
24.7854371,93.9475175
0.51740407778236
0
Approach road

Progress Update : 12/09/2019
Ongoing
1
7085969655
24.78081101453558,93.94696348014827
24.7854371,93.9475175
0.51740407778236
0
Approach road