Progress
 
 
Project Details
DAR-2019-000439
NESIDS CCPUR
Water Supply Distribution Network for Churachandpur for promoting tourism under NESIDS
13/12/2018
PHED
Churachandpur
2339.36
792.10
NESIDS
In progress
Phase l
24.80748517734833,93.94173431396518
Progress Update : 14/03/2020
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.335072,93.694792
58.16076634182
0
Water supply Distribution network for Churachandpur for promoting tourism under NESIDS on turnkey basis (Sh Providing Laying clear water distribution main)

Progress Update : 14/03/2020
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3350373,93.69497
58.156527241242
0
Water supply Distribution network for Churachandpur for promoting tourism under NESIDS on turnkey basis (Sh Providing Laying clear water distribution main)

Progress Update : 03/03/2020
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3268849,93.6917867
59.113856127304
0
Water supply Distribution network for Churachandpur for promoting tourism under NESIDS on turnkey basis (Sh Providing Laying clear water distribution main)

Progress Update : 03/03/2020
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3268261,93.6919895
59.11100402648
0
Water supply Distribution network for Churachandpur for promoting tourism under NESIDS on turnkey basis (Sh Providing Laying clear water distribution main)

Progress Update : 28/02/2020
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3455651,93.7005559
56.856378553593
0
Water supply Distribution network for Churachandpur for promoting tourism under NESIDS on turnkey basis (Sh Providing Laying distribution pipes at Rengkai zone)

Progress Update : 24/02/2020
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.32679,93.6930483
59.068971511137
0
Water supply Distribution network for Churachandpur for promoting tourism under NESIDS on turnkey basis (Sh Providing Laying clear water distribution main)

Progress Update : 23/02/2020
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3348833,93.6949967
58.170843109674
0
Water supply Distribution network for Churachandpur for promoting tourism under NESIDS on turnkey basis (Sh Providing Laying clear water distribution main)

Progress Update : 23/02/2020
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3350669,93.6947927
58.161248310871
0
Water supply Distribution network for Churachandpur for promoting tourism under NESIDS on turnkey basis (Sh Providing Laying clear water distribution main)

Progress Update : 17/02/2020
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3364319,93.6782351
58.764125111145
0
Water supply Distribution network for Churachandpur for promoting tourism under NESIDS on turnkey basis (Sh Providing Laying distribution pipes at Phailian IB zone)

Progress Update : 16/02/2020
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3290933,93.6927133
58.851727701886
0
Water supply Distribution network for Churachandpur for promoting tourism under NESIDS on turnkey basis (Sh Providing Laying clear water distribution main)

Progress Update : 16/02/2020
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3345685,93.6947357
58.213796557408
0
Water supply Distribution network for Churachandpur for promoting tourism under NESIDS on turnkey basis (Sh Providing Laying clear water distribution main)

Progress Update : 15/02/2020
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.2981261,93.6800151
62.515429435656
0
Water supply Distribution network for Churachandpur for promoting tourism under NESIDS on turnkey basis (Sh Providing Laying clear water distribution main)

Progress Update : 12/02/2020
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3057709,93.6856195
61.505235386152
0
Water supply Distribution network for Churachandpur for promoting tourism under NESIDS on turnkey basis (Sh Providing Laying clear water distribution main)

Progress Update : 12/02/2020
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3079183,93.685885
61.277318635308
0
Water supply Distribution network for Churachandpur for promoting tourism under NESIDS on turnkey basis (Sh Providing Laying clear water distribution main)

Progress Update : 10/02/2020
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3062107,93.6827664
61.583020925669
0
Water supply Distribution network for Churachandpur for promoting tourism under NESIDS on turnkey basis (Sh Providing Laying clear water distribution main)

Progress Update : 08/02/2020
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3098354,93.6862536
61.068294633302
0
Water supply Distribution network for Churachandpur for promoting tourism under NESIDS on turnkey basis (Sh Providing Laying clear water distribution main)

Progress Update : 07/02/2020
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3522274,93.7031436
56.074756302122
0
Water supply Distribution network for Churachandpur for promoting tourism under NESIDS on turnkey basis (Sh Providing Laying distribution pipes at Bijang PHE zone)

Progress Update : 07/02/2020
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3429778,93.6877378
57.681814886716
0
Water supply Distribution network for Churachandpur for promoting tourism under NESIDS on turnkey basis (Sh Providing Laying distribution pipes at Phailian IB zone)

Progress Update : 06/02/2020
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3542931,93.7038596
55.836193183592
0
Water distribution network for Churachandpur for promoting tourism under NESIDS on turnkey basis (Sh Providing Laying distribution pipes at Bijang PHE zone)

Progress Update : 27/01/2020
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3321925,93.6985491
58.288910156597
0
Water supply Distribution network for Churachandpur for promoting tourism under NESIDS on turnkey basis (Sh Providing Laying distribution pipes at Don Bosco zone)

Progress Update : 27/01/2020
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3321925,93.6985491
58.288910156597
0
Water supply Distribution network for Churachandpur for promoting tourism under NESIDS on turnkey basis (Sh Providing Laying distribution pipes at Don Bosco zone)

Progress Update : 24/01/2020
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3378875,93.710816
57.197683917112
0
Water supply Distribution network for Churachandpur for promoting tourism under NESIDS on turnkey basis (Sh Providing Laying distribution pipes at Rengkai zone)

Progress Update : 24/01/2020
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3378875,93.710816
57.197683917112
0
Water supply Distribution network for Churachandpur for promoting tourism under NESIDS on turnkey basis (Sh Providing Laying distribution pipes at Rengkai zone)

Progress Update : 16/01/2020
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3455356,93.7018711
56.802431286279
0
Water supply Distribution network for Churachandpur for promoting tourism under NESIDS on turnkey basis (Sh Providing Laying distribution pipes at Public Ground zone)

Progress Update : 16/01/2020
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.33183,93.685195
58.907551572857
0
Water supply Distribution network for Churachandpur for promoting tourism under NESIDS on turnkey basis (Sh Providing Laying distribution pipes network for phailian zone)

Progress Update : 31/12/2019
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.2911796,93.6754759
63.409908581962
0
Water supply Distribution network for Churachandpur for promoting tourism under NESIDS on turnkey basis (Sh Providing Laying clear water distribution main)

Progress Update : 31/12/2019
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.2894083,93.6764633
63.546124257102
792.1
Water supply Distribution network for Churachandpur for promoting tourism under NESIDS on turnkey basis (Sh Providing Laying clear water distribution main)

Progress Update : 29/08/2019
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3413044,93.6972055
57.429914673452
0
Water supply Distribution network for Churachandpur for promoting tourism ( sh: providing & laying distribution pipes at Don Bosco zone)

Progress Update : 29/08/2019
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3382064,93.6959134
57.797210439621
0
Water supply Distribution network for Churachandpur for promoting tourism ( sh: providing & laying distribution pipes at Don Bosco zone)

Progress Update : 29/08/2019
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3365297,93.6962709
57.950152868413
0
Water supply Distribution network for Churachandpur for promoting tourism ( sh: providing & laying distribution pipes at Don Bosco zone)

Progress Update : 29/08/2019
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3313214,93.693686
58.585630556171
0
Water supply Distribution network for Churachandpur for promoting tourism ( sh: providing & laying distribution pipes at Don Bosco zone)

Progress Update : 29/08/2019
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3292798,93.6927741
58.830346406699
0
Water supply Distribution network for Churachandpur for promoting tourism ( sh: providing & laying distribution pipes at Don Bosco zone)

Progress Update : 29/08/2019
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3294706,93.6927446
58.812441695168
0
Water supply Distribution network for Churachandpur for promoting tourism ( sh: providing & laying distribution pipes at Don Bosco zone)

Progress Update : 29/08/2019
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3286567,93.6926892
58.896669023136
0
Water supply Distribution network for Churachandpur for promoting tourism ( sh: providing & laying distribution pipes at Don Bosco zone)

Progress Update : 29/08/2019
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3277784,93.6957652
58.852864993538
0
Water supply Distribution network for Churachandpur for promoting tourism ( sh: providing & laying distribution pipes at Don Bosco zone)

Progress Update : 29/08/2019
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3250746,93.7002046
58.938125967248
0
Water supply Distribution network for Churachandpur for promoting tourism ( sh: providing & laying distribution pipes at Don Bosco zone)

Progress Update : 29/08/2019
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3265965,93.6986191
58.850898833061
0
Water supply Distribution network for Churachandpur for promoting tourism ( sh: providing & laying distribution pipes at Don Bosco zone)

Progress Update : 29/08/2019
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.343295,93.700195
57.100188615787
0
Water supply Distribution network for Churachandpur for promoting tourism (sh: providing & laying distribution pipeline at Rengkai zone)

Progress Update : 29/08/2019
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3445617,93.69932
57.010843490792
0
Water supply Distribution network for Churachandpur for promoting tourism (sh: providing & laying distribution pipeline at Sielmat zone)

Progress Update : 29/08/2019
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3446167,93.6992
57.010538548505
0
Water supply Distribution network for Churachandpur for promoting tourism (sh: providing & laying distribution pipeline at Sielmat zone)

Progress Update : 29/08/2019
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3490045,93.701321
56.477670334665
0
Water supply Distribution network for Churachandpur for promoting tourism (sh: providing & laying distribution pipeline at Sielmat zone)

Progress Update : 29/08/2019
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3511601,93.693823
56.593041635529
0
W/s distribution network for churachandpur for promoting tourism (sh: providing &Laying distribution pipeline at Sielmat zone)

Progress Update : 29/08/2019
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3515867,93.6988983
56.324899737111
0
W/s distribution network for churachandpur for promoting tourism (sh: providing &Laying distribution pipeline at Sielmat zone)

Progress Update : 29/08/2019
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3496054,93.6979849
56.563512567986
0
W/s distribution network for churachandpur for promoting tourism (sh: providing &Laying distribution pipeline at Sielmat zone)

Progress Update : 29/08/2019
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.333829,93.7062301
57.799592463782
0
W/s distribution network for churachandpur for promoting tourism (sh: Laying of pipeline at Rengkai zone)

Progress Update : 29/08/2019
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3376033,93.70917
57.294658440834
0
W/s distribution network for churachandpur for promoting tourism (sh: Laying of pipeline at Rengkai zone)

Progress Update : 29/08/2019
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3328089,93.7024244
58.062336859061
0
W/s distribution network for churachandpur for promoting tourism (sh: Laying of pipeline at Rengkai zone)

Progress Update : 29/08/2019
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3376666,93.709354
57.280602793474
0
W/s distribution network for churachandpur for promoting tourism

Progress Update : 29/08/2019
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.33491,93.70897
57.576235522303
0
W/s distribution network for churachandpur for promoting tourism

Progress Update : 29/08/2019
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3424205,93.703693
57.037966876935
0
W/s distribution network for churachandpur for promoting tourism

Progress Update : 29/08/2019
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3432007,93.7021073
57.027242524308
0
W/s distribution network for churachandpur for promoting tourism

Progress Update : 29/08/2019
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3427133,93.7014267
57.105575787251
0
Water supply distribution network for churachandpur for promoting tourism

Progress Update : 29/08/2019
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3427344,93.6999999
57.164993842491
0
Water supply distribution network for churachandpur for promoting tourism

Progress Update : 29/08/2019
In progress
Phase l
lalrindik
24.80748517734833,93.94173431396518
24.3427344,93.6999999
57.164993842491
0
Water supply distribution network for churachandpur for promoting tourism