Progress
 
 
Project Details
10(1)/2015-SD/MQCD/TSM/Kangla/Drain/22
Development of Tourist Circuit in Manipur.......(SH:Levelling, Horticulture & Storm water drain- Storm water drain work at Kangla)
29/06/2015
PWD
Imphal-West
251.06
186.98
Ministry of Tourism, GOI
Completed
Final
24.807777341236136,93.94051122665428
Construction of RCC drain, brick masonry drain, RCC slab culvert, RCC hume pipe etc
Progress Update : 05/02/2021
Completed
Final
aemqcd1
24.807777341236136,93.94051122665428
24.80875018,93.94305006
0.27813686687277
186.982
Storm water drain

Progress Update : 11/09/2019
Ongoing
5
aemqcd1
24.807777341236136,93.94051122665428
24.8116037,93.9382775
0.48149136063219
24.86
Construction of rrc culvert

Progress Update : 11/09/2019
Ongoing
5
aemqcd1
24.807777341236136,93.94051122665428
24.8087745,93.9357321
0.49492958268308
24.86
Construction of brickwork drain and rrc drain

Progress Update : 02/07/2018
Ongoing
3
aemqcd1
24.807777341236136,93.94051122665428
24.813369,93.9408921
0.62292137056503
80.44
Construction of r.c.c drain, culvert,etc.

Progress Update : 02/07/2018
Ongoing
3
aemqcd1
24.807777341236136,93.94051122665428
24.8112417,93.9379589
0.46339770789732
80.44
Construction of r.c.c drain, culvert,etc.

Progress Update : 28/03/2018
Ongoing
2
aemqcd1
24.807777341236136,93.94051122665428
24.8173924,93.9388099
1.0827953777089
170.95
Rcc drain near Western Rampart

Progress Update : 28/03/2018
Ongoing
2
aemqcd1
24.807777341236136,93.94051122665428
24.81459824,93.93969391
0.7628856009298
170.95
Rcc drain near Western Rampart

Progress Update : 28/03/2018
Ongoing
2
aemqcd1
24.807777341236136,93.94051122665428
24.8153489,93.9406114
0.84193911920366
170.95
Rcc drain near Northern Rampart

Progress Update : 27/03/2018
Ongoing
2
aemqcd1
24.807777341236136,93.94051122665428
24.80441142,93.94030737
0.3748205107007
170.95
Brickwork drain near Southern inner moat.