Progress
 
 
Project Details
DAR-2019-000372
TBL/Darpan/Plan/77
Impvt. of road from Champa Bridge to Heirok part-II, Ngarouthel upto SPO Barrack.
05/03/2019
PWD
Thoubal
100.00
0.00
State Plan
98%
2
24.590812519534463,94.07351690635983
GSB,WBM,PC,etc.
Progress Update : 14/03/2020
98%
2
sotbl2
24.590812519534463,94.07351690635983
24.570507,94.0578152
2.7600944552069
0
GSB, WBM, PC completed for 2.75km

Progress Update : 14/03/2020
98%
2
sotbl2
24.590812519534463,94.07351690635983
24.5800767,94.0645838
1.4969147095667
0
GSB, WBM, PC completed for 2.75km

Progress Update : 22/02/2020
Work In progress
1
sotbl2
24.590812519534463,94.07351690635983
24.5800621,94.0642823
1.5167826917536
0
GSB, WBM (completed)

Progress Update : 22/02/2020
Work In progress
1
sotbl2
24.590812519534463,94.07351690635983
24.5800621,94.0642823
1.5167826917536
0
GSB, WBM (completed), 1.70 km PC surface completed