Progress
 
 
Project Details
DAR-2019-000324
TBL/Darpan/Plan/75
Impvt. of road from Lamding Laikon to Sangaiyumpham Pulleipokpi road
08/03/2019
PWD
Thoubal
100.00
82.00
State Plan
100%
III
24.586917077119416,94.00524557116705
Earthwork in banking,sand gravelled,WBM ,PC, etc
Progress Update : 28/10/2021
100%
III
9612527160
24.586917077119416,94.00524557116705
24.5875607,94.0092271
0.40887549489198
82
PC

Progress Update : 28/10/2021
100%
III
9612527160
24.586917077119416,94.00524557116705
24.5878143,94.008604
0.35391475005228
82
PC

Progress Update : 28/10/2021
100%
III
9612527160
24.586917077119416,94.00524557116705
24.5850013,94.0045876
0.22316129086332
82
PC

Progress Update : 16/03/2020
98%
II
9612527160
24.586917077119416,94.00524557116705
24.5881077,94.0132014
0.81521622723318
0
2cm premix carpet

Progress Update : 16/03/2020
98%
II
9612527160
24.586917077119416,94.00524557116705
24.5849586,94.0090095
0.43846496449566
0
2cm Premix carpet

Progress Update : 16/03/2020
98%
II
9612527160
24.586917077119416,94.00524557116705
24.6181537,94.0185098
3.7230612872469
0
2cm Premix carpet

Progress Update : 21/02/2020
65%
Phase I
9612527160
24.586917077119416,94.00524557116705
24.586779,94.0094166
0.42200458745555
0
Earth work in banking, shingling and WBM

Progress Update : 21/02/2020
65%
Phase I
9612527160
24.586917077119416,94.00524557116705
24.5843273,93.9985074
0.73964602994959
0
Earth work in banking, shingling and WBM

Progress Update : 21/02/2020
65%
Phase I
9612527160
24.586917077119416,94.00524557116705
24.5843273,93.9985075
0.73963671522667
0
Earth work in banking, shingling and WBM