Progress
 
 
Project Details
DAR-2019-000138
IED/Ahallup-Heingangkhong/274
Impvt. of Ahallup Bazar to Heingangkhong via Police Station and Kairang Muslim Chingya
17/12/2018
PWD
Imphal-East
400.00
0.00
CRF
Completed
1
24.853803647211205,93.95877425347294
Progress Update : 09/10/2020
Completed
1
naoba58
24.853803647211205,93.95877425347294
24.8545778,93.9516602
0.72288879328176
0

Progress Update : 09/10/2020
CRF work
1
naoba58
24.853803647211205,93.95877425347294
24.8476431,93.9478362
1.2988874394412
0
ongoing

Progress Update : 06/03/2019
CRF work
1
robin
24.853803647211205,93.95877425347294
24.834725,93.9742912
2.6365451516987
0
On going

Progress Update : 06/03/2019
CRF work
1
robin
24.853803647211205,93.95877425347294
24.8478286,93.9688716
1.2162455788692
0
On going