Progress
 
 
Project Details
DAR-2019-000137
KMJ/Infra/1
Infrastructure Development of Kamjong,Kamjong District,Manipur.
23/03/2018
PWD
Kamjong
1708.73
800
State Plan
In Progress
Phase 3
24.859607225026234,94.51340874739071
DC bunglow,Security Barrack,Approach road,site levelling,DLO building-A&B block,etc.
Progress Update : 16/05/2020
In Progress
Phase 3
so1ukl
24.859607225026234,94.51340874739071
24.8608364,94.5109813
0.2804518571455
500
Building construction

Progress Update : 16/05/2020
In Progress
Phase 3
so1ukl
24.859607225026234,94.51340874739071
24.8594356,94.5139729
0.060029558364973
500
Building construction

Progress Update : 16/05/2020
70% Progress
Phase 3
so1ukl
24.859607225026234,94.51340874739071
24.8594347,94.5142509
0.087100794725195
800
Building - DC Bungalwo construction at completion stage

Progress Update : 16/05/2020
70 % progress
Phase 3
so1ukl
24.859607225026234,94.51340874739071
24.8598086,94.5130436
0.043109423420212
800
Building Security Barrack construction in Progress

Progress Update : 19/12/2019
In progress
2nd phase
so1ukl
24.859607225026234,94.51340874739071
24.8616391,94.5095787
0.44759899863065
0
Building construction

Progress Update : 19/12/2019
In progress
2nd phase
so1ukl
24.859607225026234,94.51340874739071
24.8593234,94.5137878
0.049581567183519
0
Building construction

Progress Update : 19/12/2019
In progress
2nd phase
so1ukl
24.859607225026234,94.51340874739071
24.8616391,94.5095787
0.44759899863065
0
Building construction

Progress Update : 07/03/2019
On progress
1
so1ukl
24.859607225026234,94.51340874739071
24.858648,94.5126702
0.1301045662917
0
approach road

Progress Update : 07/03/2019
On progress
1
so1ukl
24.859607225026234,94.51340874739071
24.8588506,94.5128602
0.10069917915159
0
approach road

Progress Update : 07/03/2019
On progress
1
so1ukl
24.859607225026234,94.51340874739071
24.8591902,94.5141211
0.085527478036438
0
Building

Progress Update : 07/03/2019
On progress
1
so1ukl
24.859607225026234,94.51340874739071
24.8594655,94.514002
0.061891196227401
0
Building

Progress Update : 07/03/2019
On progress
1
so1ukl
24.859607225026234,94.51340874739071
24.859324,94.5140189
0.069144184199337
0
Building

Progress Update : 07/03/2019
On progress
1
so1ukl
24.859607225026234,94.51340874739071
24.8593234,94.5140351
0.070632865419488
0
Building