Progress
 
 
Project Details
DAR-2019-000065
MANIDCO_C&I_19
ESTABLISHMENT OF FACTORY WORKSHEDS AT NEW INDUSTRIAL ESTATE T.M. KASOM, UKHRUL, MANIPUR
21/03/2017
Commerce and Industries
Ukhrul
1231.50
647.90
MANIDCO
NEC
In progress
Phase 1
24.959264446519107,94.21919073164474
ESTABLISHMENT OF FACTORY WORKSHEDS AT NEW INDUSTRIAL ESTATE T.M. KASOM, UKHRUL, MANIPUR
Progress Update : 06/11/2019
In progress
Phase 1
SadanandaSO
24.959264446519107,94.21919073164474
24.9551147,94.2152358
0.60979310280102
0
CONSTRUCTION OF FACTORY WORKSHEDS No. 20,21,22,23,24 AT NEW INDUSTRIAL ESTATE T.M. KASOM, UKHRUL, MANIPUR.

Progress Update : 06/11/2019
In progress
Phase 1
SadanandaSO
24.959264446519107,94.21919073164474
24.9524515,94.2046672
1.648456951002
0
CONSTRUCTION OF FACTORY WORKSHEDS 16, 17,18,19 AT NEW INDUSTRIAL ESTATE T.M. KASOM, UKHRUL, MANIPUR.

Progress Update : 06/11/2019
In progress
Phase 1
SadanandaSO
24.959264446519107,94.21919073164474
24.9583822,94.2174779
0.19858383425344
0
CONSTRUCTION OF FACTORY WORKSHEDS 11 & 12 AT NEW INDUSTRIAL ESTATE T.M. KASOM, UKHRUL, MANIPUR.

Progress Update : 06/11/2019
In progress
Phase 1
SadanandaSO
24.959264446519107,94.21919073164474
24.9583822,94.2174779
0.19858383425344
0
CONSTRUCTION OF FACTORY WORKSHEDS 13, 14 & 15 AT NEW INDUSTRIAL ESTATE T.M. KASOM, UKHRUL, MANIPUR.

Progress Update : 06/11/2019
In progress
Phase 1
SadanandaSO
24.959264446519107,94.21919073164474
24.9565589,94.216517
0.40391083687648
0
CONSTRUCTION OF FACTORY WORKSHEDS 7, 8, 9 &10 AT NEW INDUSTRIAL ESTATE T.M. KASOM, UKHRUL, MANIPUR.

Progress Update : 06/11/2019
In progress
Phase 1
SadanandaSO
24.959264446519107,94.21919073164474
24.9524515,94.2046672
1.648456951002
0
CONSTRUCTION OF FACTORY WORKSHEDS 4, 5 & 6 AT NEW INDUSTRIAL ESTATE T.M. KASOM, UKHRUL, MANIPUR.

Progress Update : 06/11/2019
In progress
Phase 1
SadanandaSO
24.959264446519107,94.21919073164474
24.9524515,94.2046672
1.648456951002
0
CONSTRUCTION OF FACTORY WORKSHEDS 2 & 3 AT NEW INDUSTRIAL ESTATE T.M. KASOM, UKHRUL, MANIPUR.

Progress Update : 06/11/2019
In progress
Phase 1
SadanandaSO
24.959264446519107,94.21919073164474
24.9529664,94.2126735
0.96021987773857
0
CONSTRUCTION OF FACTORY WORKSHEDS NO.1 AT NEW INDUSTRIAL ESTATE T.M. KASOM, UKHRUL, MANIPUR

Progress Update : 23/03/2019
In progress
I
SadanandaSO
24.959264446519107,94.21919073164474
24.95924166,94.21957375
0.038693327913074
0
CONSTRUCTION O FACTORY WORK SHEDS AT TM KASOM , UKHRUL

Progress Update : 23/03/2019
In progress
I
SadanandaSO
24.959264446519107,94.21919073164474
24.95927828,94.21957696
0.03896429493523
0
Workshed

Progress Update : 23/03/2019
In progress
I
SadanandaSO
24.959264446519107,94.21919073164474
24.95848766,94.22041149
0.15034456458429
0
Workshed

Progress Update : 23/03/2019
In progress
I
SadanandaSO
24.959264446519107,94.21919073164474
24.95850719,94.22041702
0.14956805821316
0
Workshed

Progress Update : 23/03/2019
In progress
I
SadanandaSO
24.959264446519107,94.21919073164474
24.9588,94.22036818
0.12944096652535
0
Workshed

Progress Update : 23/03/2019
In progress
I
SadanandaSO
24.959264446519107,94.21919073164474
24.95879332,94.22035781
0.12878339434048
0
Workshed

Progress Update : 23/03/2019
In progress
I
SadanandaSO
24.959264446519107,94.21919073164474
24.96106123,94.21944292
0.20139451008568
0
Workshed

Progress Update : 23/03/2019
In progress
I
SadanandaSO
24.959264446519107,94.21919073164474
24.96026615,94.21938983
0.11317280026473
0
Workshed

Progress Update : 09/02/2019
In progress
Phase-I
LembaSO
24.959264446519107,94.21919073164474
24.9604884,94.2193193
0.13670664647924
0
ESTABLISHMENT OF FACTORY WORKSHEDS AT T.M. KASOM, UKHRUL, MANIPUR.

Progress Update : 09/02/2019
In progress
Phase-I
LembaSO
24.959264446519107,94.21919073164474
24.9604699,94.2192982
0.13447097986209
0
ESTABLISHMENT OF FACTORY WORKSHEDS AT T.M. KASOM, UKHRUL, MANIPUR.

Progress Update : 09/02/2019
In progress
Phase-I
LembaSO
24.959264446519107,94.21919073164474
24.960469,94.2193078
0.13445271648541
0
ESTABLISHMENT OF FACTORY WORKSHEDS AT T.M. KASOM, UKHRUL, MANIPUR.

Progress Update : 09/02/2019
In progress
Phase-I
LembaSO
24.959264446519107,94.21919073164474
24.9604348,94.2193542
0.13117029432607
0
ESTABLISHMENT OF FACTORY WORKSHEDS AT T.M. KASOM, UKHRUL, MANIPUR.

Progress Update : 09/02/2019
In progress
Phase-I
LembaSO
24.959264446519107,94.21919073164474
24.9592887,94.2193173
0.013040801379304
0
ESTABLISHMENT OF FACTORY WORKSHEDS AT T.M. KASOM, UKHRUL, MANIPUR.

Progress Update : 09/02/2019
In progress
Phase-I
LembaSO
24.959264446519107,94.21919073164474
24.9593094,94.2193313
0.015025768458299
0
ESTABLISHMENT OF FACTORY WORKSHEDS AT T.M. KASOM, UKHRUL, MANIPUR.

Progress Update : 09/02/2019
In progress
Phase-I
LembaSO
24.959264446519107,94.21919073164474
24.9590784,94.2195557
0.042207787085269
0
ESTABLISHMENT OF FACTORY WORKSHEDS AT T.M. KASOM, UKHRUL, MANIPUR.

Progress Update : 09/02/2019
In progress
Phase-I
LembaSO
24.959264446519107,94.21919073164474
24.9591652,94.2196801
0.05055023518307
0
ESTABLISHMENT OF FACTORY WORKSHEDS AT T.M. KASOM, UKHRUL, MANIPUR.

Progress Update : 09/02/2019
In progress
Phase-I
LembaSO
24.959264446519107,94.21919073164474
24.9587174,94.2205341
0.1484523595504
0
ESTABLISHMENT OF FACTORY WORKSHEDS AT T.M. KASOM, UKHRUL, MANIPUR.

Progress Update : 09/02/2019
In progress
Phase-I
LembaSO
24.959264446519107,94.21919073164474
24.9585103,94.2204747
0.15422004839765
0
ESTABLISHMENT OF FACTORY WORKSHEDS AT T.M. KASOM, UKHRUL, MANIPUR.