Project Details
DAR-2019-000047
EE/HS/Impvt. of Heiningsoi W/Supply/36.
Impvt. of Heiningsoi Water Supply road at Yumnam Huidrom Makha.
26/03/2018
PWD
Imphal-West
42.23
6
State Plan
In progress
Phase 1
24.648847725790077,93.90314495770258
1) E/W. in formation banking & Widening for a length of 690m 2) Sand shingling, 3) Constn. of 1.5m span slab culverts- 2Nos.
Progress Update : 26/11/2020
In progress
Phase 1
mfrahman
24.648847725790077,93.90314495770258
24.6466577,93.899742
0.42138218990248
0
Earthworks in formation banking and widening, GSB, WBM III & Slab culverts

Progress Update : 11/01/2020
In progress
Phase 1
mfrahman
24.648847725790077,93.90314495770258
24.6566696,93.8994237
0.94752924037675
6
Earthworks, GSB, WBM III. 3 m wide, slab culvert

Progress Update : 08/01/2020
In progress
Phase one
mfrahman
24.648847725790077,93.90314495770258
24.6470776,93.8978319
0.57186803955752
6
E/w,gsb,wbm& slab culvert