DAR-2019-000015
EE/HS/Impvt. of Langthabal Kunja/35.
Impvt. of Langthabal Kunja Mutum Lambi IVR connecting NH- 39.
28/02/2018
PWD
Imphal-West
33.77
0.00
State Plan
Completed
1
24.73460379420819,93.93724755566404
1. E/W. in embankment for the length of 1.10Kms. with an average height of 0.50 to 0.65m. 2. Sand shingle with a thickness of 0.225m as per IRC specification. 3. WBM IRC- II.
Progress Update : 18/02/2019
Completed
1
mfrahman
24.73460379420819,93.93724755566404
24.7352443,93.9314315
0.59165544134404
18
Culvert

Progress Update : 18/02/2019
Completed
1
mfrahman
24.73460379420819,93.93724755566404
24.7398605,93.9341359
0.66360623602844
18
Culvert

Progress Update : 06/02/2019
Completed
1
mfrahman
24.73460379420819,93.93724755566404
24.7335552,93.9344545
0.30521492145661
18
Road work

Progress Update : 06/02/2019
Completed
1
mfrahman
24.73460379420819,93.93724755566404
24.7245985,93.9370031
1.1127583372272
18
Road work

Progress Update : 06/02/2019
Completed
1
mfrahman
24.73460379420819,93.93724755566404
24.7327227,93.9379589
0.22115111562886
18
Road work

Progress Update : 15/01/2019
Completed
1
mfrahman
24.73460379420819,93.93724755566404
24.7338549,93.9375955
0.090379639468956
18
Road work