Project Details
DAR-2019-000005
MQCD/Darpan/IT Cafeteria Bldg/2018-19/36
Construction of Cafeteria and Renovation of existing buildings in IT Park Campus at Mantripukhri(SH:-Construction of Cafeteria)
16/05/2016
PWD
Imphal-East
275.74
0.00
State Plan
completed
5th and final RA bill
24.842621,93.94114609999997
Construction of Cafeteria bldg. of G+2 RCC structure i/c flooring, doors & windows, finishing items, water supply & sanitary installation, etc.
Progress Update : 09/05/2024
completed
5th and final RA bill
aemqcd3
24.842621,93.94114609999997
24.8424929,93.9416882
0.056522461689013
0
RCC pathways, false ceiling, sanitary works, finishing works, etc.

Progress Update : 17/01/2024
Completed
4th RA bill
aemqcd3
24.842621,93.94114609999997
24.8426779,93.9414749
0.033774000588864
0
Flooring works in all floors and staircase, sanitary works, doors and windows, landscaping and roof treatment.

Progress Update : 17/01/2024
Completed
4th RA bill
aemqcd3
24.842621,93.94114609999997
24.8426917,93.9414743
0.034035811253336
0
Flooring works in all floors and staircase, sanitary works, doors and windows, landscaping and roof treatment.

Progress Update : 17/01/2024
Completed
4th RA bill
aemqcd3
24.842621,93.94114609999997
24.8424002,93.9414903
0.042531298109429
0
Flooring works in all floors and staircase, sanitary works, doors and windows, landscaping and roof treatment.

Progress Update : 17/01/2024
Completed
4th RA bill
aemqcd3
24.842621,93.94114609999997
24.8426483,93.9415048
0.036320155099787
0
Flooring works in all floors and staircase, sanitary works, doors and windows, landscaping and roof treatment.

Progress Update : 17/01/2024
Completed
4th RA bill
aemqcd3
24.842621,93.94114609999997
24.8427101,93.9414259
0.029919750737797
0
Flooring works in all floors and staircase, sanitary works, doors and windows, landscaping and roof treatment.

Progress Update : 17/01/2024
Completed
4th RA bill
aemqcd3
24.842621,93.94114609999997
24.842689,93.941432
0.029821851010864
0
Flooring works in all floors and staircase, sanitary works, doors and windows, landscaping and roof treatment.

Progress Update : 06/01/2022
Ongoing
NA
aemqcd3
24.842621,93.94114609999997
24.8430281,93.9418075
0.080638668648671
96.62
Brickwork, Plastering, Wood work, RCC Works in slab, beams, Stairs, Mumty

Progress Update : 06/01/2022
Ongoing
NA
aemqcd3
24.842621,93.94114609999997
24.8426704,93.9412935
0.015854568855453
96.62
Brickwork, Plastering, Wood work, RCC Works in slab, beams, Stairs, Mumty

Progress Update : 06/01/2022
Ongoing
NA
aemqcd3
24.842621,93.94114609999997
24.8426704,93.9412935
0.015854568855453
96.62
Brickwork, Plastering, Wood work, RCC Works in slab, beams, Stairs, Mumty

Progress Update : 23/09/2019
Ongoing
2nd phase
aemqcd3
24.842621,93.94114609999997
24.8428821,93.9414583
0.042838695211718
58.75
Casting of columns and slab along with beams

Progress Update : 07/01/2019
Ongoing
Phase 1
aemqcd3
24.842621,93.94114609999997
24.8427353,93.9415206
0.039867403279575
0
Foundation, casting of columns, brickwork, sand filling up to plinth

Progress Update : 07/01/2019
Ongoing
Phase 1
aemqcd3
24.842621,93.94114609999997
24.8427516,93.9419296
0.08037830419331
0
Foundation, casting of columns, brickwork, sand filling up to plinth

Progress Update : 07/01/2019
Ongoing
Phase 1
aemqcd3
24.842621,93.94114609999997
24.8427709,93.9419515
0.082956966672084
0
Foundation, casting of columns, brickwork, sand filling up to plinth