Progress
 
 
Project Details
DAR-2018-001074
AAI/18-Toi-KGHS-IW
Construction of Toilet in Kwakeithel Girls High School, Imphal West, Manipur.
29/03/2018
Education (S)
Imphal-West
9.52
6.33
Airport Authority of India
Completed
Nil
24.789061597569876,93.92359507605738
Construction of Toilet in Kwakeithel Girls High School, Imphal West, Manipur.
Progress Update : 13/09/2019
Completed
Nil
so4.eew-mn
24.789061597569876,93.92359507605738
24.78915189,93.92370648
0.015075167393988
0
front view (gents)

Progress Update : 13/09/2019
Completed
Nil
so4.eew-mn
24.789061597569876,93.92359507605738
24.7894743,93.9233478
0.052237785583981
0
front view (ladies)

Progress Update : 13/09/2019
Completed
Nil
so4.eew-mn
24.789061597569876,93.92359507605738
24.7894743,93.9233478
0.052237785583981
0
Front view (Toilet)

Progress Update : 04/12/2018
In progess
Nill
sur1.eew-mn
24.789061597569876,93.92359507605738
24.7894293,93.9223503
0.13213702981371
0
In toilet

Progress Update : 04/12/2018
In progess
Nill
sur1.eew-mn
24.789061597569876,93.92359507605738
24.7894293,93.9223503
0.13213702981371
0
In toilet

Progress Update : 04/12/2018
In progess
Nill
sur1.eew-mn
24.789061597569876,93.92359507605738
24.7894293,93.9223503
0.13213702981371
0
Front view

Progress Update : 25/07/2018
The work is in progress
1st Phase
sur2.eew-mn
24.789061597569876,93.92359507605738
24.7892257,93.9235456
0.018917910692482
0
The work has been completed upto plint level

Progress Update : 25/07/2018
The work is in progress
1st Phase
sur2.eew-mn
24.789061597569876,93.92359507605738
24.7892842,93.9239052
0.039907844896284
0
The work has been completed upto plint level