Progress
 
 
Project Details
DAR-2018-001018
AUG_LAIRENJAM WSS
Improvement of Lairenjam wss treatment units
23/10/2017
PHED
Imphal-West
75.00
13
CSS / CPS
Ongoing
2
24.725781505326704,93.88198289323748
Construction of additional ground reservoir , and replacement of distribution main.
Progress Update : 25/06/2018
Ongoing
2
henthoi
24.725781505326704,93.88198289323748
24.72536,93.883826666667
0.19202081696519
13
Augmentation of Lairenjam WSS (Sh :- Construction of additional reservoir)