Progress
 
 
Project Details
DAR-2018-000956
WRD-YAS-04
Repairing & renovation of Main Hostel, KLSC, Imphal
2018-03-06
Water Resources Department (WRD)
Imphal-East
214.88
214.88
State Plan
Completed
Phase I
24.820156557916782,93.9558148962708
The project involves repairing to plaster, paint & floor of four blocks of YAS Hostel No. 2. It involves IEI & WSSI and also flooring with tiles for the floor of bathroom, toillets, kitchen & dining hall.
Progress Update : 2018-05-20
Completed
Phase I
QCMD
24.820156557916782,93.9558148962708
24.8200417,93.9559333
0.017489425249024
Approved
2018-05-25 11:29:03
approverifcd
0
Repair and renovation of YAS Main Hostel No. 2, KLSC, Imphal (sh:iei and WSSI of Block III)

Progress Update : 2018-05-20
Completed
Phase I
QCMD
24.820156557916782,93.9558148962708
24.8200767,93.95602
0.022523203592018
Approved
2018-05-25 11:32:00
approverifcd
0
Repair and renovation of YAS Main Hostel No. 2, KLSC, Imphal (sh: Block III)

Progress Update : 2018-05-20
Completed
Phase I
QCMD
24.820156557916782,93.9558148962708
24.82019,93.9560483
0.023846705327521
Approved
2018-05-25 11:21:49
approverifcd
0
Repair and renovation of YAS Main Hostel No. 2, KLSC, Imphal (sh: Block II)

Progress Update : 2018-05-20
Completed
Phase I
QCMD
24.820156557916782,93.9558148962708
24.820165,93.9560167
0.020387355164768
Approved
0
Repair and renovation of YAS Main Hostel No. 2, KLSC, Imphal (sh: iei and wssi ofBlock II)

Progress Update : 2018-05-20
Completed
Phase I
QCMD
24.820156557916782,93.9558148962708
24.8228378,93.9493655
0.71588913031947
Approved
2018-05-25 11:26:53
approverifcd
0
Repair and renovation of YAS Main Hostel No. 2, KLSC, Imphal (sh: iei and wssi ofBlock II)

Progress Update : 2018-05-20
Completed
Phase I
QCMD
24.820156557916782,93.9558148962708
24.8201724,93.955955
0.014248467028674
Approved
2018-05-25 11:34:50
approverifcd
0
Repair and renovation of YAS Main Hostel No. 2, KLSC, Imphal (sh: Block IV)

Progress Update : 2018-05-20
Completed
Phase I
QCMD
24.820156557916782,93.9558148962708
24.8201054,93.9558153
0.0056887195725389
Approved
2018-05-25 11:02:26
approverifcd
0
Repair and renovation of YAS Main Hostel No. 2, KLSC, Imphal (sh: Block- I)

Progress Update : 2018-05-20
Completed
Phase I
QCMD
24.820156557916782,93.9558148962708
24.8197612,93.9519788
0.38962338223909
Approved
2018-05-25 11:05:22
approverifcd
0
Repair and renovation of YAS Main Hostel No. 2, KLSC, Imphal (sh:IEI and WSSI of Block In)

Progress Update : 2018-05-20
Completed
Phase I
QCMD
24.820156557916782,93.9558148962708
24.8201317,93.9556767
0.014217758748755
Approved
2018-05-25 11:20:36
approverifcd
0
Repair and renovation of YAS Main Hostel No. 2, KLSC, Imphal (sh: Block I)

Foundation & Inauguration
-
-
-

-
-
-