Progress
 
 
Project Details
IFC-TMP-1
Thoubal Multipurpose Project
01/05/1980
Water Resources Department (WRD)
169427.00
154804.30
Ministry of Water Resources
ongoing
7
24.8299745,94.14420599999994
Progress Update : 11/03/2025
ongoing
7
TFD
24.8299745,94.14420599999994
24.7056886,94.0940247
14.71873548813
0
name of work construction of canal work for a length of 60 m along the canal near changamdabi loukhol phase 3

Progress Update : 11/03/2025
ongoing
7
TFD
24.8299745,94.14420599999994
24.7060998,94.0935616
14.692020152217
0
name of work construction of canal work for a length of 60 m along the canal near changamdabi loukol phase 3

Progress Update : 08/03/2025
Completed
8th Revised
TPD-2
24.8299745,94.14420599999994
24.8244251,94.1433462
0.62310588511179
0
TMP, C-WORKS SH- Major repairing work of Gate Shaft at Thoubal Dam

Progress Update : 08/03/2025
Completed
8th Revised
TPD-2
24.8299745,94.14420599999994
24.82154,94.1479217
1.0100114121631
0
TMP,C-Works SH-Repairing of approach road to Thoubal Dam terminal gate from D/S southern side along with CC drain from RD 0.00-45m, 60m-250m and 350m-500m

Progress Update : 08/03/2025
completed
8th Revised
TPD-2
24.8299745,94.14420599999994
24.8225985,94.1440225
0.8203433469516
0
TMP,C-works SH Re-construction of Toe drain at the downstream slope of Thoubal Dam

Progress Update : 08/03/2025
completed
8th Revised
TPD-2
24.8299745,94.14420599999994
24.8213433,94.1424233
0.97641548349605
0
TMP,C-works SH Premix carpeting of approach road with CC drains from Tail Race Channel starting from RCC Bridge to Maphou Police station

Progress Update : 24/09/2024
ongoing
8th Revised
TPD-4
24.8299745,94.14420599999994
24.6810131,94.1032349
17.071776348288
0
Construction of Bridge at Rd.1.025 km of Heirok Branch Canal

Progress Update : 29/06/2024
ongoing
7
TFD
24.8299745,94.14420599999994
24.7046663,94.09374
14.835364584701
0
name of work construction of canal work for a length of 60 m along the canal near changamdabi loukol phase 2

Progress Update : 29/06/2024
ongoing
7
TFD
24.8299745,94.14420599999994
24.7046356,94.0936575
14.841432859756
0
name of work construction of canal work for a length of 60 m along the canal near changamdabi loukol phase 1

Progress Update : 29/06/2024
ongoing
7
TFD
24.8299745,94.14420599999994
24.704798,94.093797
14.819634261496
0
name of work construction of canal lining for trmc at Rd 6415 m for thoubal multipurpose project

Progress Update : 08/05/2024
on going
7th Revised
TPD-4
24.8299745,94.14420599999994
24.625993,94.0868885
23.407682350724
0
TMP L-Earthwork SH- Construction of valve chamber for laying of DI pipes for canal water of Heirok branch canal,Thoubal Multipurpose project from Rd.4.00km to 8.60km

Progress Update : 08/05/2024
ongoing
7
TFD
24.8299745,94.14420599999994
24.7339772,94.0531946
14.083472521009
0
tmp l earthwork construction of retaining wall at Rd 1020 m to Rd 1060 m of Sanapat branch canal of trmc

Progress Update : 08/05/2024
ongoing
7
TFD
24.8299745,94.14420599999994
24.733887,94.0529467
14.10740724762
0
tmp l earthwork construction of retaining wall at Rd 1060 m to Rd 1100m of Sanapat branch canal of trmc

Progress Update : 08/05/2024
on going
7th revised
TPD-4
24.8299745,94.14420599999994
24.6731648,94.0485503
19.932206815192
0
TMP-D-Regulator SH- Improvement of cross Regulator at Rd.00Km of charangpat Branch canal,Thoubal Multipurpose project

Progress Update : 08/05/2024
ongoing
7
TFD
24.8299745,94.14420599999994
24.7078769,94.0916187
14.577220440447
0
tmp l earthwork construction of protection work at Rd 7.720 km of trmc

Progress Update : 08/05/2024
ongoing
7
TFD
24.8299745,94.14420599999994
24.7075432,94.0917612
14.606563350014
0
tmp l earthwork construction of protection work at Rd 7.695 km of trmc

Progress Update : 08/05/2024
ongoing
7
TFD
24.8299745,94.14420599999994
24.6939572,94.0895252
16.099907323669
0
tmp l earthwork construction of protection work at Rd 7.665 km of trmc

Progress Update : 08/05/2024
ongoing
7
TFD
24.8299745,94.14420599999994
24.7070246,94.0920551
14.649632475658
0
Tmp l earthwork construction of protection work at Rd 7.605 km of trmc

Progress Update : 08/05/2024
ongoing
7
TFD
24.8299745,94.14420599999994
24.7069801,94.0920795
14.653365311988
0
Tmp l earthwork construction of protection work at Rd 7.575 km of trmc

Progress Update : 08/05/2024
on going
7th revised
TPD-4
24.8299745,94.14420599999994
24.5344933,94.017335
35.266297497494
0
construction of bridge at RD.5.013km of Lousi distributary canal

Progress Update : 08/05/2024
on going
7th revised
TPD-4
24.8299745,94.14420599999994
24.5441567,94.0206
34.145343232729
0
construction of Bridge at RD.0.750km and foot bridge at RD.3.520km and RD.5.550km of Lousi distributary canal

Progress Update : 08/05/2024
on going
7th revised
TPD-4
24.8299745,94.14420599999994
24.5468433,94.0204883
33.871604100727
0
construction of Lousi distributary canal from RD.2.490km to RD.3.710km

Progress Update : 08/05/2024
on going
7th revised
TPD-4
24.8299745,94.14420599999994
24.5521633,94.0198217
33.347752569332
0
construction of foot bridge at RD.4.450km of Lousi distributary canal

Progress Update : 08/05/2024
on going
7th revised
TPD-4
24.8299745,94.14420599999994
24.5681271,94.0302077
31.309414153912
0
construction of CC protection work on L/S and R/S bund of Lousi distributary canal from RD.0.00 to RD.0.180km

Progress Update : 08/05/2024
on going
7th revised
TPD-4
24.8299745,94.14420599999994
24.5841317,94.0349499
29.478892342196
0
resectioning of canal from RD.26.50km to RD.27.76km of LMC

Progress Update : 23/01/2024
Ongoing
6 Revised
TFD
24.8299745,94.14420599999994
24.73986,94.0409653
14.457260330111
0
TMP, U-Disty. SH- Construction of side drain at the inspection path from RD.25.750 Km to RD. 25.940 Km. of TRMC

Progress Update : 18/01/2024
Ongoing
6 Revised
TFD
24.8299745,94.14420599999994
24.7059485,94.0259652
18.239659727384
0
TMP, L-Earth Work-SH-Construction of canal lining at R.D.12.410 Km. of Thoubal Right Main Canal

Progress Update : 18/01/2024
Ongoing
6 Revised
TFD
24.8299745,94.14420599999994
24.7052588,94.0240504
18.424440164625
0
TMP-L-Earth Work - SH - Construction of canal lining at R.D.12.60 Km. of Thoubal Right Main Canal

Progress Update : 14/01/2024
Completed
8th Revised
TPD-2
24.8299745,94.14420599999994
24.8828073,94.1269095
6.1281633026382
0
TMP, C-Works (SH: Construction of Mechanical Lift House and hoisting arrangements of Lift at Control Shaft of Thoubal Dam)

Progress Update : 10/01/2024
On going
7th
TPD-4
24.8299745,94.14420599999994
24.6816597,94.1013816
17.048528692041
0
Laying of MS pipe 1400mm dia for Heirok branch canal from RD.0.700km to Rd.1.400km

Progress Update : 13/11/2023
Ongoing
7
TFD
24.8299745,94.14420599999994
24.7016143,94.0983321
15.005015850706
0
Name of work - construction of canal lining for TRMC at RD 7.198 km for TMP

Progress Update : 29/04/2023
On going
6th revised
TPD-4
24.8299745,94.14420599999994
24.6522916,94.0927071
20.429493397651
0
TMP,L-E/Work-SH-Laying of DI pipe 150 mm dia. For distributary at Rd. 4.444 km L/S of Heirok branch canal, Thoubal multipurpose project.

Progress Update : 29/04/2023
On going
6th revised
TPD-4
24.8299745,94.14420599999994
24.6633822,94.0926022
19.242322432151
0
TMP,L-E-Work-SH-Laying of DI pipe 150 mm dia. For distributary at Rd. 3.703 km of Heirok branch canal, Thoubal multipurpose project

Progress Update : 28/04/2023
On going
6th revised
TPD-4
24.8299745,94.14420599999994
24.6506652,94.0871376
20.753528690629
0
TMP,L-E-WORK-SH - Laying of DI pipe 150 mm Dia. & 100 mm Dia. for distributary at RD. 1.912 km , RD 2.334 km, RD 3.351 km and 4.417 km of Heirok Branch canal, thoubal multipurpose project

Progress Update : 28/04/2023
On going
6th Revised
TPD-4
24.8299745,94.14420599999994
24.6665737,94.0987788
18.738591884561
0
TMP.L-E/Work-SH-Laying of DI pipe 1000mm dia. For canal water of Heirok Branch Canal Thoubal Multipurpose project for RD.no.4.847 km to RD no.5.447 km

Progress Update : 26/04/2023
On going
6th Revised
TPD-4
24.8299745,94.14420599999994
24.6532783,94.0857166
20.515399767126
0
TMP, L-E-work SH-Laying of DI pipe 150 mm Dia for distributary at RD.2.818 km of Heirok Branch Canal, Thoubal Multipurpose project

Progress Update : 18/04/2023
On going
6th Revised
TPD-4
24.8299745,94.14420599999994
24.6855918,94.1077279
16.470943346575
0
Laying of MS pipe 1000mm dia from pump house to reservoir at RD0.00km of HBC

Progress Update : 28/03/2023
In progest
6th revised
TPD-4
24.8299745,94.14420599999994
24.5792475,94.0812048
28.595370333497
0
TMP,L - Earth works SH- Laying of DI pipe 1000mm dia. for canal water of Heirok Branch canal , Thoubal Multipurpose project Rd.11.847km to Rd.12.047km

Progress Update : 26/03/2023
On going
6th Revised
TPD-4
24.8299745,94.14420599999994
24.5792475,94.0812048
28.595370333497
0
TMP,L-E Works SH -Laying of DI pipe 250mm.dia. for distributary at RD.11.667 km.Left side of Heirok Branch Canal, Thoubal Multipurpose Project

Progress Update : 19/03/2023
Ongoing
IV
TFD
24.8299745,94.14420599999994
24.7492608,94.0406475
13.777504120393
0
TMP, L-Earth Work (Construction of protection work at RD.16.165 Km. of Thoubal Right Main Canal)

Progress Update : 19/03/2023
Ongoing
IV
TFD
24.8299745,94.14420599999994
24.7494939,94.0457553
13.373144002114
0
TMP, L-Earth Work (Construction of Canal Lining for Thoubal Right Main Canal at RD. 19.20 Km. to RD .19.28 KM.

Progress Update : 19/03/2023
Ongoing
IV
TFD
24.8299745,94.14420599999994
24.7257879,94.0320291
16.200221493147
0
TMP, L-Earth Work (Construction of Canal Lining for Thoubal Right Main Canal at RD. 19.28 Km. to RD .19.32 KM.

Progress Update : 19/03/2023
Ongoing
IV
TFD
24.8299745,94.14420599999994
24.7360132,94.0374553
15.009376743634
0
TMP, L-Earth Work (Construction of Canal Lining at RD. 19.40 Km. Of Thoubal Right Main Canal)

Progress Update : 19/03/2023
Ongoing
6th RCE
TPD-6
24.8299745,94.14420599999994
24.8251171,94.0428821
10.239148670258
0
Construction of distributary canal of Water Transmission System at Sajenbam Sangsabi

Progress Update : 19/03/2023
Ongoing
6th RCE
TPD-6
24.8299745,94.14420599999994
24.8240148,94.0425628
10.27854450372
0
Construction of distributary canal of Water Transmission System at Takhel

Progress Update : 19/03/2023
Ongoing
6th RCE
TPD-6
24.8299745,94.14420599999994
24.8240148,94.0425628
10.27854450372
0
Construction of outlet for disty. At takhel and thrust block at p2 of T2

Progress Update : 18/03/2023
On going
6th RCE
TPD-6
24.8299745,94.14420599999994
24.8170038,94.1368228
1.6233026893615
0
RCC Tunnel1 lining

Progress Update : 18/03/2023
On going
6th RCE
TPD-6
24.8299745,94.14420599999994
24.8338059,94.1451387
0.43628458657745
0
Protection work of di pipe at spillway

Progress Update : 17/03/2023
On Going
6th Revised
TPD-4
24.8299745,94.14420599999994
24.6820879,94.1003768
17.028561219486
0
Laying of MS pipe 1400mm dia for canal water of HBC , TMP from Rd 2.100km to Rd 2.800km

Progress Update : 17/03/2023
On Going
6th Revised
TPD-4
24.8299745,94.14420599999994
24.6824583,94.1003768
16.988793387026
0
Laying of MS pipe 1400mm dia for canal water of HBC , TMP from Rd 1.400km to Rd 2.100km

Progress Update : 10/02/2023
On going
6th revised
TPD-4
24.8299745,94.14420599999994
24.6053123,94.0764129
25.901544890086
0
TMP,L-E/Works(SH:-Laying of DI pipe 1000mm dia for canal water of Heirok Branch Canal,Thoubal Multipurpose project from Rd.10.847km to Rd.11.447km)

Progress Update : 06/02/2023
Ongoing
7th
TFD
24.8299745,94.14420599999994
24.7420959,94.038125
14.496505828619
0
Name of work:-T.M.P. L/Earthwork(Sh:- Construction of Trough Super passage at RD 17.440 km of Thoubal Right Main Canal.)

Progress Update : 09/01/2023
On going
6th Revised
TPD-4
24.8299745,94.14420599999994
24.62089515,94.08849833
23.918577074705
0
TMP-L- E/Works ( SH;- Laying of DI pipe 1000 mm dia for canal water of HBC, TMP from RD. 10.247 km to RD 10.847 km)

Progress Update : 25/10/2022
Ongoing
7th Revised
TFD
24.8299745,94.14420599999994
24.7509066,94.0509589
12.879792074162
0
Construction of protection work of TRMC at RD 16.005 km of TMP

Progress Update : 25/10/2022
Ongoing
7th Revised
TFD
24.8299745,94.14420599999994
24.7602605,94.0585271
11.613769630252
0
Construction of canal linning of TRMC at RD 14.200 Km of TMP

Progress Update : 12/07/2022
Ongoing
6th Revised
TPD-4
24.8299745,94.14420599999994
24.6444449,94.0677886
22.02516231798
0
Name of work ; Laying of M.S & D.I pipe of Main & Distributary canal of Heirok Branch Canal , Thoubal Multipurpose project .

Progress Update : 12/07/2022
Ongoing
6th Revised
TPD-4
24.8299745,94.14420599999994
24.6477618,94.0684274
21.657207053512
0
Name of work ; Laying of M.S & D.I pipe of Main & Distributary canal of Heirok Branch Canal , Thoubal Multipurpose project .

Progress Update : 22/02/2022
On going
6th Revised
TPD-4
24.8299745,94.14420599999994
24.6893056,94.1082114
16.057597604738
0
TMP, L-E/W (SH: Construction of outer compound wall around the reservoir at RD 0.155 km of HBC)

Progress Update : 22/02/2022
On going
6th Revised
TPD-4
24.8299745,94.14420599999994
24.6893056,94.1082114
16.057597604738
0
TMP, L-E/W (SH: Construction of Fencing Compound Drain and Office building at RD0.00 km of HBC)

Progress Update : 22/02/2022
On going
6th Revised
TPD-4
24.8299745,94.14420599999994
24.6893056,94.1082114
16.057597604738
0
TMP, L-E/W (SH: Construction of Pump house and trough at RD0.00 km of HBC)

Progress Update : 22/02/2022
On going
6th Revised
TPD-4
24.8299745,94.14420599999994
24.6893056,94.1082114
16.057597604738
0
TMP, L-E/W (SH: Earthwork excavation and pilling for Pump house and sump well at RD 0.00km of HBC)

Progress Update : 22/02/2022
On going
6th Revised
TPD-4
24.8299745,94.14420599999994
24.6893056,94.1082114
16.057597604738
0
TMP, L-E/W (SH: Construction of Sump Well at RD 0.00 km of Heirok Branch Canal)

Progress Update : 22/02/2022
Ongoing
6th revised
TPD-4
24.8299745,94.14420599999994
24.6444964,94.0796075
21.630409142439
0
TMP-L- Earthwork( SH:- Supply and delivery of M.S and D.I as per specification along with necessary supply , delivery of bends and valves ......)

Progress Update : 22/02/2022
Ongoing
6th revised
TPD-4
24.8299745,94.14420599999994
24.6444964,94.0796075
21.630409142439
0
TMP-L- Earthwork( SH:- Supply and delivery of M.S and D.I as per specification along with necessary supply , delivery of bends and valves ......)

Progress Update : 22/02/2022
Ongoing
6th revised
TPD-4
24.8299745,94.14420599999994
24.6423847,94.0891923
21.585249949907
0
TMP-L- Earthwork( SH:- Supply and delivery of M.S and D.I as per specification along with necessary supply , delivery of bends and valves ......)

Progress Update : 22/02/2022
Ongoing
6th revised
TPD-4
24.8299745,94.14420599999994
24.64469243,94.05266173
22.580608208218
0
TMP-L- Earthwork( SH:- Strengthning of canal embankment adjoining with Aaron stream syphon at RD. 17.310 of LMC)

Progress Update : 22/02/2022
Ongoing
6th revised
TPD-4
24.8299745,94.14420599999994
24.6487865,94.0578885
21.951118508378
0
TMP-D-Regulator ( SH:- providing and fixing of M/S shutter at RD. 17.30 LMC

Progress Update : 22/02/2022
Ongoing
6th revised
TPD-4
24.8299745,94.14420599999994
24.6471915,94.0483094
22.512882834337
0
TMP-D-Regulator ( SH:- providing and fixing of M/S shutter at RD. 17.30 LMC

Progress Update : 22/02/2022
Ongoing
Phase 6
TPD-4
24.8299745,94.14420599999994
24.651318,94.0463938
22.184938059263
0
TMP-D-Regulator ( SH:- providing and fixing of M/S shutter at RD. 13.915 LMC

Progress Update : 22/02/2022
Ongoing
Phase 6
TPD-4
24.8299745,94.14420599999994
24.67328982,94.04913325
19.891570957915
0
TMP-D-Regulator ( SH:- providing and fixing of M/S shutter at RD. 1.518 km of CBC

Progress Update : 22/02/2022
Ongoing
Phase 6
TPD-4
24.8299745,94.14420599999994
24.6727785,94.0499871
19.900031165184
0
TMP-D-Regulator ( SH:- providing and fixing of M/S shutter at RD. 12.457

Progress Update : 22/02/2022
Ongoing
Phase 6
TPD-4
24.8299745,94.14420599999994
24.67343478,94.04921428
19.873502819873
0
TMP-D-Regulator ( SH:- providing and fixing of M/S shutter at RD. 13.739

Progress Update : 22/02/2022
Ongoing
Phase 6
TPD-4
24.8299745,94.14420599999994
24.672769,94.0499876
19.900934977605
0
TMP-D-Regulator ( SH:- providing and fixing of M/S shutter at RD. 13.736

Progress Update : 22/02/2022
Ongoing
Phase 6
TPD-4
24.8299745,94.14420599999994
24.6760772,94.0478617
19.683781104773
0
TMP-L Earthwork ( SH:- Supply and delivery of MS and DI as per specification along with necessary supply , delivery of venda and valves .......)

Progress Update : 22/02/2022
Ongoing
Phase 6
TPD-4
24.8299745,94.14420599999994
24.6760772,94.0478617
19.683781104773
0
TMP-L Earthwork ( SH:- Supply and delivery of MS and DI as per specification along with necessary supply , delivery of venda and valves .......)

Progress Update : 22/02/2022
Ongoing
Phase 6
TPD-4
24.8299745,94.14420599999994
24.67435369,94.04710843
19.888022021924
0
TMP-L Earthwork ( SH:- Supply and delivery of MS and DI as per specification along with necessary supply , delivery of venda and valves .......)

Progress Update : 20/02/2022
Completed
1 st
TPD-2
24.8299745,94.14420599999994
24.8132923,94.1371427
1.9871352729769
0
TMP-C, Works: (SH: Repairing of Exit Channel protection work of Thoubal Spillway from RD 933.63 m to 1068.20 m)

Progress Update : 20/02/2022
Completed
1 st
TPD-2
24.8299745,94.14420599999994
24.820195,94.1419401
1.1111610151117
0
TMP-C, Works: (SH: Construction of Compound wall on the Southern Side of Thoubal Multipurpose Project for a length of 248 m)

Progress Update : 20/02/2022
Completed
1 st
TPD-2
24.8299745,94.14420599999994
24.6853913,94.11508
16.342919112338
0
TMP-C, Works: (SH: Construction of Compound wall on the Southern Side of Thoubal Multipurpose Project for a length of 248 m)

Progress Update : 20/02/2022
Completed
1 st
TPD-2
24.8299745,94.14420599999994
24.820195,94.1419401
1.1111610151117
0
TMP-C, Works: (SH: Construction of Compound wall on the Southern Side of Thoubal Multipurpose Project for a length of 115 m upto river)

Progress Update : 20/02/2022
Completed
1 st
TPD-2
24.8299745,94.14420599999994
24.8754914,94.1371427
5.1109310857415
0
TMP-C, Works: (SH: Construction of Compound wall on the Southern Side of Thoubal Multipurpose Project for a length of 115 m upto river)

Progress Update : 20/02/2022
Completed
1 st
TPD-2
24.8299745,94.14420599999994
24.816005,94.140535
1.5968311461196
0
TMP-C, Works: (SH: Construction of Compound wall on the Southern Side of Thoubal Multipurpose Project for a length of 115 m upto river)

Progress Update : 20/02/2022
Completed
1 st
TPD-2
24.8299745,94.14420599999994
24.8754914,94.1371427
5.1109310857415
0
TMP-C, Works: (SH: Construction of Compound wall on the Southern Side of Thoubal Multipurpose Project for a length of 144 m along the river with DMC piling)

Progress Update : 20/02/2022
Completed
1 st
TPD-2
24.8299745,94.14420599999994
24.820195,94.1419401
1.1111610151117
0
TMP-C, Works: (SH: Construction of Compound wall on the Southern Side of Thoubal Multipurpose Project for a length of 144 m along the river with DMC piling)

Progress Update : 08/10/2021
Ongoing
6th RCE
TPD-2
24.8299745,94.14420599999994
24.8219668,94.1448188
0.8925177326473
0
TMP,C-Works (SH: Erection of inaugural stone of Thoubal Dam) 1.

Progress Update : 08/10/2021
Ongoing
6th RCE
TPD-2
24.8299745,94.14420599999994
24.8360892,94.1428997
0.69255129433647
0
TMP,C-Works (SH: Erection of inaugural stone of Thoubal Dam) 1.

Progress Update : 06/10/2021
In progress
6th Revised
TPD-4
24.8299745,94.14420599999994
24.6884246,94.107547
16.168257251372
0
Construction of outer compound fencing around the reservoir at RD. 0.155km of HBC

Progress Update : 06/10/2021
In progress
6th Revised
TPD-4
24.8299745,94.14420599999994
24.6884246,94.107547
16.168257251372
0
Construction of Reservior at RD 0.155km of HBC and compound fencing

Progress Update : 06/10/2021
In progress
6th Revised
TPD-4
24.8299745,94.14420599999994
24.6894557,94.1085467
16.03370492543
0
Earthwork excavation and pilling for pump house and sump well at RD 0.00km of HBC

Progress Update : 06/10/2021
In progress
5th Revised
TPD-4
24.8299745,94.14420599999994
24.6894557,94.1085467
16.03370492543
0
Construction of fencing, compound drain and office building at RD 0.00km of HBC

Progress Update : 06/10/2021
In progress
6th Revised
TPD-4
24.8299745,94.14420599999994
24.6894536,94.1085481
16.033900725718
0
Construction of pump house and trough at RD 0.00km of HBC

Progress Update : 06/10/2021
In progress
6th Revised
TPD-4
24.8299745,94.14420599999994
24.6790146,94.0560604
18.998858606276
0
Construction of sump well at RD 0.00km of HBC

Progress Update : 06/10/2021
Ongoing
VI
TFD
24.8299745,94.14420599999994
24.7232864,94.0796521
13.534868619785
0
TMP, F-CD works (SH:- Providing protection work at R.D. 9.105 km to 9.130 km of Thoubal Right Main Canal)

Progress Update : 06/10/2021
Ongoing
VI
TFD
24.8299745,94.14420599999994
24.7232864,94.0796521
13.534868619785
0
TMP, F-CD works (SH:- Providing protection work at R.D. 9.105 km to 9.130 km of Thoubal Right Main Canal)

Progress Update : 06/10/2021
Ongoing
6 revised
TFD
24.8299745,94.14420599999994
24.6998843,94.0241946
18.869129744675
0
Construction of protection work at D/S of bridge at RD 23.500 km of TRMC

Progress Update : 06/10/2021
Ongoing
VI
TFD
24.8299745,94.14420599999994
24.7142214,94.0805531
14.385678527969
0
TMP, L- Earth Work ( SH : - Construction of protection work at R.D. 8.660 Km. of TRMC )

Progress Update : 06/10/2021
Ongoing
VI
TFD
24.8299745,94.14420599999994
24.7142214,94.0805531
14.385678527969
0
TMP, L- Earth Work ( SH : - Construction of protection work at R.D. 8.640 Km. of TRMC )

Progress Update : 06/10/2021
Ongoing
VI
TFD
24.8299745,94.14420599999994
24.7142214,94.0805531
14.385678527969
0
TMP, L- Earth Work ( SH : - Construction of protection work at R.D. 8.620 Km. of TRMC )

Progress Update : 06/10/2021
Ongoing
6th revised
TPD-4
24.8299745,94.14420599999994
24.6727954,94.0467131
20.058543396181
0
1000mmm DI PIPE

Progress Update : 06/10/2021
Ongoing
6th revised
TPD-4
24.8299745,94.14420599999994
24.67318107,94.04689612
20.012103910147
0
100mmm DI PIPE

Progress Update : 06/10/2021
Ongoing
6 revised
TFD
24.8299745,94.14420599999994
24.7427109,94.0394624
14.350723211685
0
Construction of trough superpassage at RD 17.980km of TRMC

Progress Update : 06/10/2021
Ongoing
6 revised
TFD
24.8299745,94.14420599999994
24.7427109,94.0394624
14.350723211685
0
Construction of protection work at RD 17.990 km of TRMC

Progress Update : 06/10/2021
Ongoing
6th revised
TPD-4
24.8299745,94.14420599999994
24.6763348,94.0390514
20.113964783381
0
900mm DI PIPE

Progress Update : 06/10/2021
Ongoing
6 revised
TFD
24.8299745,94.14420599999994
24.7403815,94.0375265
14.670018713437
0
Construction of protection work at RD 18.145 km of TRMC

Progress Update : 06/10/2021
Ongoing
6th revised
TPD-4
24.8299745,94.14420599999994
24.64530369,94.07257869
21.770273657085
0
700mm DI PIPE

Progress Update : 06/10/2021
Ongoing
6th revised
TPD-4
24.8299745,94.14420599999994
24.6630463,94.0234122
22.209919803606
0
1000mm DI PIPE

Progress Update : 06/10/2021
Ongoing
6 revised
TFD
24.8299745,94.14420599999994
24.7399138,94.0373071
14.721623525141
0
Construction of protection work at RD 18.260 km of TRMC

Progress Update : 06/10/2021
Ongoing
6 revised
TFD
24.8299745,94.14420599999994
24.7389605,94.0374381
14.784314696827
0
Construction of protection work at RD 18.280 km of TRMC

Progress Update : 06/10/2021
Ongoing
6 revised
TFD
24.8299745,94.14420599999994
24.7389605,94.0374381
14.784314696827
0
Construction of protection work at RD 18.372 km of TRMC

Progress Update : 06/10/2021
Ongoing
6 revised
TFD
24.8299745,94.14420599999994
24.7229165,94.080404
13.534646681934
0
Construction of protection work at RD 9.425 km of TRMC

Progress Update : 06/10/2021
Ongoing
6 revised
TFD
24.8299745,94.14420599999994
24.7140818,94.0805923
14.397803290751
0
Construction of protection work at RD 8.660 km of TRMC

Progress Update : 06/10/2021
Ongoing
6 revised
TFD
24.8299745,94.14420599999994
24.7140818,94.0805923
14.397803290751
0
Construction of protection work at RD 8.620 km of TRMC

Progress Update : 05/10/2021
On going
6th revised
TPD-4
24.8299745,94.14420599999994
24.8151262,93.9106396
23.628573511977
0
Tees and bends

Progress Update : 16/04/2021
Ongoing
6thRCE
TPD-6
24.8299745,94.14420599999994
24.819206666667,94.139065
1.3048436718741
0
Steel fabrication works for Bridge across the spillway to carry 1m dia DI pipes for WTS

Progress Update : 16/04/2021
Ongoing
6thRCE
TPD-6
24.8299745,94.14420599999994
24.819045,94.13921
1.3156804063025
0
Layaing of DI pipe at rd 145m to 275m

Progress Update : 16/04/2021
Ongoing
6thRCE
TPD-6
24.8299745,94.14420599999994
24.818951666667,94.13913
1.3283642326015
0
Steel fabrication works of construction of bridge across the spillway to carry DI pipe

Progress Update : 16/04/2021
Ongoing
6thRCE
TPD-6
24.8299745,94.14420599999994
24.81962,94.139251666667
1.2551844314004
0
Name of work..Laying of DI pipe for rd 275m to 410m for WTS, work includes embankment and layaing of Pipes

Progress Update : 15/04/2021
Ongoing
6th revised
TPD-4
24.8299745,94.14420599999994
24.68875,94.10805
16.121461754029
0
Construction of Sump well and pump house of Heirok Branch Canal at Rd.0.00 km

Progress Update : 15/04/2021
Ongoing
6th revised
TPD-4
24.8299745,94.14420599999994
24.688633333333,94.107805
16.139712781082
0
Construction of Reservoir for Heirok Branch Canal

Progress Update : 13/04/2021
In progress
6th Phase
TPD-4
24.8299745,94.14420599999994
24.5682149,94.0296945
31.319445194488
0
Construction of RCC Distributary canal at RD.29.115km of LMC ,Ch 240m to 455m

Progress Update : 13/04/2021
In progress
6th Phase
TPD-4
24.8299745,94.14420599999994
24.5681793,94.0300313
31.310575712165
0
Construction of RCC Distributary canal at RD.29.115km of LMC ,Ch 30m to 100m

Progress Update : 13/04/2021
In progress
6th Phase
TPD-4
24.8299745,94.14420599999994
24.5682039,94.0297638
31.317997172709
0
Construction of RCC Distributary canal at RD.29.115km of LMC ,Ch 100m to 170m

Progress Update : 13/04/2021
In progress
6th Phase
TPD-4
24.8299745,94.14420599999994
24.5907422,94.029868
28.999108218301
0
Construction of retaining wall on L/S and R/S bund of LMC from RD.25.992km to 26.100km

Progress Update : 13/04/2021
In progress
6th Phase
TPD-4
24.8299745,94.14420599999994
24.5908219,94.029808
28.99339308647
0
Construction of retaining wall on L/S and R/S bund of LMC from RD.26.105km to 26.265km

Progress Update : 12/04/2021
On going
6th RCE
TPD-6
24.8299745,94.14420599999994
24.8311966,94.0508637
9.4201964858127
0
WTS tunnel 2 p2 sluice valce chamber

Progress Update : 12/04/2021
On going
6th RCE
TPD-6
24.8299745,94.14420599999994
24.8311966,94.0508637
9.4201964858127
0
WTS tunnel 2 p2 sluice valce chamber

Progress Update : 12/04/2021
On going
6th RCE
TPD-6
24.8299745,94.14420599999994
24.8192183,94.0419244
10.390842011862
0
WTS tunnel 2 p2 block

Progress Update : 12/04/2021
On going
6th RCE
TPD-6
24.8299745,94.14420599999994
24.8081133,93.9723783
17.510365314109
0
WTS Chingkhei

Progress Update : 01/03/2021
Completed
On going 6th revised
TPD-4
24.8299745,94.14420599999994
24.6793856,94.066138
18.506638094662
0
D-regulator at RD. 12.457 km of LMC

Progress Update : 01/03/2021
Completed
On going 6th revised
TPD-4
24.8299745,94.14420599999994
24.6862201,94.068449
17.719969710396
0
D-regulator at RD. 11.60 km of LMC

Progress Update : 01/03/2021
Completed
On going 6th revised
TPD-4
24.8299745,94.14420599999994
24.6819969,94.0764129
17.820659211388
0
D-regulator at RD. 10.90 km of LMC

Progress Update : 28/02/2021
Ongoing
6 revised
TFD
24.8299745,94.14420599999994
24.8250586,93.9527883
19.324261588277
0
Construction of Protection wall at D/s of bridge at RD.23.500Km. of Thoubal Right Main Canal

Progress Update : 28/02/2021
Ongoing
6th Revised
TFD
24.8299745,94.14420599999994
24.7456086,94.0387322
14.19000536827
0
Construction of RCC Trough Super-passage at RD 17.980 Km of TRMC

Progress Update : 28/02/2021
Ongoing
6th Revised
TFD
24.8299745,94.14420599999994
24.74243926,94.03899056
14.406250248698
0
Construction of protection work at RD 17.990 Km of TRMC

Progress Update : 28/02/2021
Ongoing
6th Revised
TFD
24.8299745,94.14420599999994
24.73981618,94.03736188
14.724961010654
0
Construction of RCC Trough Super-passage at RD 18.280 Km

Progress Update : 28/02/2021
Ongoing
6
TFD
24.8299745,94.14420599999994
24.73570438,94.03817034
14.981649092446
0
Construction of outlet and distributary at RD 18.900 Km

Progress Update : 28/02/2021
Ongoing
6 revised
TFD
24.8299745,94.14420599999994
24.7143518,94.0802719
14.385422218423
0
Construction of Protection work at RD.8.620Km. of Thoubal Right Main Canal

Progress Update : 28/02/2021
On going
6th RCE
TPD-6
24.8299745,94.14420599999994
24.8217554,94.1390616
1.0510392979202
0
Pipe laying near steel bridge maphou

Progress Update : 28/02/2021
On going
6th RCE
TPD-6
24.8299745,94.14420599999994
24.8221169,94.1393814
1.000182645566
0
Steel girder for steel bridge maphou

Progress Update : 28/02/2021
On going
6th RCE
TPD-6
24.8299745,94.14420599999994
24.824638,94.1419401
0.63589689831313
0
Steel girder for steel bridge maphou

Progress Update : 27/02/2021
On going
6th RCE
TPD-6
24.8299745,94.14420599999994
24.8065899,93.9739724
17.375704363696
0
Steep pipe laying chingkheiching

Progress Update : 09/12/2018
Ongoing
V
TPD-4
24.8299745,94.14420599999994
24.6750694,94.0447976
19.935270476917
0
Side drain at RD 0.00km to RD 0.087 km of CBC

Progress Update : 08/12/2018
Ongoing project
6re
TFD
24.8299745,94.14420599999994
24.7316525,94.0364465
15.422618163928
0
Regulator

Progress Update : 07/12/2018
Ongoing
6 RCE
TFD
24.8299745,94.14420599999994
24.7063318,94.0923615
14.710513130583
0
Protection on L/S bund RD. 7.250 Km. to RD. 7.330 Km. of TRMC

Progress Update : 07/12/2018
Ongoing
6 RCE
TFD
24.8299745,94.14420599999994
24.7072907,94.12025
13.853914911748
0
Construction of drainage cum Irrigation Channel at D/S of Escape at R.D. 3.000 km of Thoubal Right Main Canal

Progress Update : 07/12/2018
Ongoing
6 RCE
TFD
24.8299745,94.14420599999994
24.7052859,94.1205225
14.068759586913
0
Protection work at D/S of Escape at RD 3.00 km of TRMC

Progress Update : 06/12/2018
Ongoing
6 RCE
TFD
24.8299745,94.14420599999994
24.74066,94.0592717
13.119954535258
0
Construction of irrigation channel at RD. 12.05 Km. of TRMC

Progress Update : 06/12/2018
Ongoing
6 RCE
TFD
24.8299745,94.14420599999994
24.7394998,94.0602175
13.156163360822
0
Providing and laying NP3 RCC 900mm pipe from RD 12.000 to RD 12.220pp km of TRMC

Progress Update : 06/12/2018
Ongoing
6 RCE
TFD
24.8299745,94.14420599999994
24.7418227,94.0594426
13.010994582593
0
Providing and laying NP3 RCC 900mm pipe from RD 12.220 to RD 12.280 km of TRMC

Progress Update : 06/12/2018
Ongoing
6 RCE
TFD
24.8299745,94.14420599999994
24.7450873,94.0618661
12.576700522595
0
Providing and laying NP3 RCC 900mm pipe from RD 12.480 to RD 12.680 km of TRMC

Progress Update : 06/12/2018
Ongoing
6RCE
TFD
24.8299745,94.14420599999994
24.7431876,94.0493068
13.597415301958
0
Trough superpassage at RD 18.36 of TRMC

Progress Update : 05/12/2018
Completed
5th revised
TPD-4
24.8299745,94.14420599999994
24.6055788,94.0250078
27.703242031303
0
U-Disty ( Contn. of CC channel at Rd 13.939 km, 19.90 km and Rd 24.65 km of LMC, Ch. 100 m)

Progress Update : 05/12/2018
Ongoing
6 RCE
TFD
24.8299745,94.14420599999994
24.749993,94.0646588
11.981847955034
0
laying of NP3 RCC 900mm pipe from RD 13.400 to 13.600 km of TC

Progress Update : 05/12/2018
Completed
5th revised
TPD-4
24.8299745,94.14420599999994
24.6764912,94.0470324
19.685372385657
0
D-Regulator (Repairing of cross regulator at Rs 13.939 km of LMC)

Progress Update : 02/12/2018
On gojng
5th Rdvised
TPD-1
24.8299745,94.14420599999994
24.8226181,94.14340429
0.82194634905153
0
D/S Drainage L/S drain

Progress Update : 01/12/2018
Completed
5th revised
TPD-4
24.8299745,94.14420599999994
24.5868967,94.03433219
29.217634699719
0
Construction of irrigation channel from rd.26.70 km to rd.26.87 km of LMC

Progress Update : 01/12/2018
In progress
5th revised
TPD-4
24.8299745,94.14420599999994
24.68957133,94.10791492
16.035632260347
0
Construction of Cross Regulator at Rd.5.950 km of LMC

Progress Update : 23/07/2017
Ongoing
Fifth revise
TPD-6
24.8299745,94.14420599999994
24.8197681,94.1116694
3.4740210890118
0
WTS- Tunnel 1 portal 2

Progress Update : 23/07/2017
Ongoing
Fifth revise
TPD-6
24.8299745,94.14420599999994
24.8052593,93.9822622
16.572963061468
0
Wts pipes

Progress Update : 21/07/2017
Ongoing
5RCE
TPD-6
24.8299745,94.14420599999994
24.8110355,94.1384219
2.1852251249951
0
WTS Tunnel 1

Progress Update : 21/07/2017
Ongoing
5RCE
TPD-6
24.8299745,94.14420599999994
24.8191783,94.1358183
1.4688410577783
0
WTS

Progress Update : 21/07/2017
Ongoing
5RCE
TPD-6
24.8299745,94.14420599999994
24.8195529,94.1348612
1.4940100569166
0
WTS

Progress Update : 20/07/2017
In progress
5th revised
TPD-2
24.8299745,94.14420599999994
24.8234495,94.1384224
0.9311327061316
0
Water supply pipeline

Progress Update : 20/07/2017
In progress
5th revised
TPD-2
24.8299745,94.14420599999994
24.8221506,94.1429254
0.87948249410109
0
Water conductor system

Progress Update : 20/07/2017
In progress
5th revised
TPD-2
24.8299745,94.14420599999994
24.8697242,94.1045316
5.9630308109029
0
Pipe Culvert

Progress Update : 20/07/2017
In progress
5th revised
TPD-2
24.8299745,94.14420599999994
24.8703162,94.1396471
4.5090983230309
0
Link road ramrei to lamlai khunou

Progress Update : 20/07/2017
In progress
5th revised
TPD-2
24.8299745,94.14420599999994
24.8703162,94.1396471
4.5090983230309
0
Link road ramrei to lamlai khunou

Progress Update : 19/07/2017
Ongoing
5RCE
TPD-6
24.8299745,94.14420599999994
24.8365509,94.0555995
8.9709821303919
0
WTS TUNNEL 2

Progress Update : 19/07/2017
Ongoing
5thRevised
TPD-1
24.8299745,94.14420599999994
24.8724592,94.1397012
4.7456705847184
0
Railling

Progress Update : 19/07/2017
Ongoing
5thRevised
TPD-1
24.8299745,94.14420599999994
24.9692711,94.2241181
17.459762812636
0
Dam railing street lighting

Progress Update : 18/07/2017
Ongoing
5th revise
TFD
24.8299745,94.14420599999994
24.7594633,94.0625283
11.37714629636
0
F-CD- cut and cover@RD 14.640 km to 14.662km

Progress Update : 18/07/2017
Ongoing
5th revise
TFD
24.8299745,94.14420599999994
24.7527327,94.0492672
12.868670265637
0
F-CD work- Contn. Of 0.70 m span trough super passage at RD 15.24 km of TRMC

Progress Update : 18/07/2017
Ongoing
5th revise
TFD
24.8299745,94.14420599999994
24.6912583,94.082675
16.62799359741
0
U-Disty &Minors- Contn. of RCC slab covered PCC drain of Yambem Disty. at RD 1890 m to 2235 m

Progress Update : 18/07/2017
Ongoing
5th revise
TFD
24.8299745,94.14420599999994
24.6943618,94.0919467
15.975242034081
0
U-Disty & Minors- Contn. of Yambem dusty. 0 m to 1740 m- Phase 1

Progress Update : 18/07/2017
ongoing
5th revise
TFD
24.8299745,94.14420599999994
24.7034179,94.0923876
15.012849974355
0
U-Disty &Minors- Contn. of Changamdabi disty canal at RD 5.60 km of TRMC i/c one head regulators

Progress Update : 18/07/2017
ongoing
5th revise
TFD
24.8299745,94.14420599999994
24.6558398,94.0984592
19.905433085778
0
H-Escape- Contn. of canal escape cum DO at RD 5.35 km of TRMC

Progress Update : 18/07/2017
ongoing
5th revise
TFD
24.8299745,94.14420599999994
24.70492352,94.1197999
14.121016096423
0
H-Escape-Repairing of Canal escape to thoubal river at RD 3.0 km at Nungbrang and rising of bund from RD 3.0 km to 3.240 km of TRMC

Progress Update : 18/07/2017
Ongoing
5th revise
TFD
24.8299745,94.14420599999994
24.710494531319,94.119995422661
13.507917756393
0
L-E/W- P/Wall@RD 2.735 km to 2.885 km of TRMC

Progress Update : 17/07/2017
Ongoing
5th revised
TPD-1
24.8299745,94.14420599999994
24.91272474,94.16665568
9.4755703213162
0
RR

Progress Update : 17/07/2017
Ongoing
5th revised
TPD-1
24.8299745,94.14420599999994
24.92198064,94.17254034
10.621894332223
0
RR

Progress Update : 16/07/2017
Ongoing
5thRevisex
TPD-1
24.8299745,94.14420599999994
24.82369186,94.13807714
0.93301416218625
0
Control room

Progress Update : 14/07/2017
Ongoing
5thRevised
TPD-1
24.8299745,94.14420599999994
24.8230389,94.14737648
0.83490274223872
0
Compoundwall, app. Road

Progress Update : 13/07/2017
Ongoing
5th revise
TFD
24.8299745,94.14420599999994
24.7096975,94.0229634
18.129674333204
0
Construction of head regulator at R.D 22.490km of TRMC

Progress Update : 13/07/2017
Ongoing
5th revise
TFD
24.8299745,94.14420599999994
24.6936985,94.0080529
20.459088089244
0
Construction of TRMC from R.D 25.00 to RD 25.570 km

Progress Update : 12/07/2017
Ongoing
5th Revised
TPD-1
24.8299745,94.14420599999994
24.82249595,94.14054983
0.90971648616009
0
Dam and catch water drain

Progress Update : 12/07/2017
Ongoing
5th Revised
TPD-1
24.8299745,94.14420599999994
24.82353745,94.13823797
0.93540638870709
0
Dam and the steel railing

Progress Update : 10/07/2017
ongoing
5th revised
TPD-6
24.8299745,94.14420599999994
24.8197083,94.1121467
3.4307401809516
0
Water transmission system