Progress
 
 
Project Details
DAR-2018-000824
IED/Kangla Inner Moat/210
M/o internal approach rod from Museum via IRB office upto Old British...................................... western side of Kangla Inner Moat
24/03/2018
PWD
Imphal-West
54.11
43
State Plan
Completed
---
24.80748517734833,93.94173431396518
Progress Update : 01/02/2019
Completed
---
shibadatta
24.80748517734833,93.94173431396518
24.8087284,93.9356851
0.62599314036299
43
Maint of Road

Progress Update : 29/03/2018
Completed
NA
shibadatta
24.80748517734833,93.94173431396518
24.8076725,93.9403117
0.14508614838228
43
Road improvement