Progress
 
 
Project Details
DAR-2018-000575
IED/Waiton-Pourabi/154
Impvt. of road from Waiton to Pourabi via Wairi Maniyaiskul
28/02/2018
PWD
Imphal-East
76.15
40.00
State Plan
Completed
2
24.87660905044195,93.99167036820063
Progress Update : 07/10/2021
Completed
2
naoba58
24.87660905044195,93.99167036820063
24.8694894,93.9927819
0.79953230674111
0
completed

Progress Update : 22/03/2018
Completed
1
robin
24.87660905044195,93.99167036820063
24.86985869,93.99292894
0.76123161133853
40
State work

Progress Update : 22/03/2018
On going
1
robin
24.87660905044195,93.99167036820063
24.86990455,93.99294379
0.75645730038565
0
State work