Progress
 
 
Project Details
DAR-2018-000545
01
Upgradation of urban slum Phase-II at ward No 1,2,6,7,8 & 9 of Lamsang Nagar Panchayat.
17/02/2018
MAHUD
Imphal-West
1290.44
866.15
Planning and Development Authority (PDA)
CSS / CPS
Inprogress
phase -2
24.818401900028217,93.87271571159386
(i) Construction of Low Cost Latrines & Shelter Upgradation (In Progress) (ii) Improvement of Roads. (iii) Construction of drain, Community Ponds & Stalls. (iv) Construction of Ring Culvert, Crematorium with waiting shed, Club cum Library, Community Halls and Play ground. N.B:- Sl.No. (ii) has been already completed on 28-07-2014. Sl.No. (iii) & (iv) has been already completed on 22-04-2015.
Progress Update : 20/08/2020
Inprogress
phase -2
pdamapp2
24.818401900028217,93.87271571159386
24.8204607,93.8682345
0.50687850003943
0
construction of night shelter and low cost Latrine

Progress Update : 20/08/2020
Inprogress
phase -2
pdamapp2
24.818401900028217,93.87271571159386
24.8204607,93.8682345
0.50687850003943
0
construction of night shelter and low cost Latrine

Progress Update : 20/08/2020
Inprogress
phase -2
pdamapp2
24.818401900028217,93.87271571159386
24.8319472,93.8536012
2.4472700766207
0
construction of night shelter and low cost Latrine

Progress Update : 20/08/2020
Inprogress
phase -2
pdamapp2
24.818401900028217,93.87271571159386
24.8147123,93.8659684
0.79498180399732
0
construction of night shelter and low cost Latrine

Progress Update : 20/08/2020
Inprogress
phase -2
pdamapp2
24.818401900028217,93.87271571159386
24.8144588,93.8659865
0.80835256284659
0
construction of night shelter and low cost Latrine

Progress Update : 20/08/2020
Inprogress
phase -2
pdamapp2
24.818401900028217,93.87271571159386
24.8147461,93.8666223
0.73716057728355
0
construction of night shelter and low cost Latrine

Progress Update : 20/08/2020
Inprogress
phase -2
pdamapp2
24.818401900028217,93.87271571159386
24.8124026,93.874659
0.69529307859997
0
construction of night shelter and low cost Latrine

Progress Update : 20/08/2020
Inprogress
phase -2
pdamapp2
24.818401900028217,93.87271571159386
24.8118437,93.8749701
0.76387367783757
0
construction of night shelter and low cost Latrine

Progress Update : 20/08/2020
Inprogress
phase -2
pdamapp2
24.818401900028217,93.87271571159386
24.8157868,93.8771438
0.53315873792543
0
construction of night shelter and low cost Latrine

Progress Update : 20/08/2020
Inprogress
phase -2
pdamapp2
24.818401900028217,93.87271571159386
24.8105759,93.8637805
1.2531524149958
0
construction of night shelter and low cost Latrine

Progress Update : 20/08/2020
Inprogress
phase -2
pdamapp2
24.818401900028217,93.87271571159386
24.8138931,93.8805421
0.93552494865356
0
construction of night shelter and low cost Latrine

Progress Update : 20/08/2020
Inprogress
phase -2
pdamapp2
24.818401900028217,93.87271571159386
24.8165114,93.8723933
0.21270733743928
0
construction of night shelter and low cost Latrine

Progress Update : 20/08/2020
Inprogress
phase -2
pdamapp2
24.818401900028217,93.87271571159386
24.8138931,93.8805421
0.93552494865356
0
construction of night shelter and low cost Latrine

Progress Update : 20/08/2020
Inprogress
phase -2
pdamapp2
24.818401900028217,93.87271571159386
24.8204607,93.8682345
0.50687850003943
0
construction of night shelter and low cost Latrine

Progress Update : 20/08/2020
Inprogress
phase -2
pdamapp2
24.818401900028217,93.87271571159386
24.8319472,93.8536012
2.4472700766207
0
construction of night shelter and low cost Latrine

Progress Update : 20/08/2020
Inprogress
phase -2
pdamapp2
24.818401900028217,93.87271571159386
24.8319472,93.8536012
2.4472700766207
0
construction of night shelter and low cost Latrine

Progress Update : 20/08/2020
Inprogress
phase -2
pdamapp2
24.818401900028217,93.87271571159386
24.8363358,93.8522771
2.8688482654419
0
construction of night shelter and low cost Latrine

Progress Update : 20/08/2020
In progress
Phase -II
pdamapp2
24.818401900028217,93.87271571159386
24.8391141,93.8485124
3.3569416223391
0
Construction of night shelter and Low cost Latrine at Lamsang Nagar Panchayat

Progress Update : 24/07/2020
in progress
Phase -II
pdamapp2
24.818401900028217,93.87271571159386
24.8142884,93.867835
0.67217683863101
0
construction of Night Shelter and low cost latrine

Progress Update : 24/07/2020
in progress
Phase -II
pdamapp2
24.818401900028217,93.87271571159386
24.8120833,93.8771438
0.83265235793157
0
construction of Night Shelter and low cost latrine

Progress Update : 24/07/2020
in progress
Phase -II
pdamapp2
24.818401900028217,93.87271571159386
24.8139723,93.872035
0.49729343379166
0
construction of Night Shelter and low cost latrine

Progress Update : 24/07/2020
in progress
Phase -II
pdamapp2
24.818401900028217,93.87271571159386
24.8157868,93.8771438
0.53315873792543
0
construction of Night Shelter and low cost latrine

Progress Update : 24/07/2020
in progress
Phase -II
pdamapp2
24.818401900028217,93.87271571159386
24.8173834,93.8721154
0.12843366550486
0
construction of Night Shelter and low cost latrine

Progress Update : 24/07/2020
in progress
Phase -II
pdamapp2
24.818401900028217,93.87271571159386
24.8035359,93.9332594
6.3300828890723
0
construction of Night Shelter and low cost latrine

Progress Update : 24/07/2020
in progress
Phase -II
pdamapp2
24.818401900028217,93.87271571159386
24.8166845,93.8717002
0.21672118188868
0
construction of Night Shelter and low cost latrine

Progress Update : 24/07/2020
in progress
Phase -II
pdamapp2
24.818401900028217,93.87271571159386
24.8137214,93.8797837
0.88298478908125
0
construction of Night Shelter and low cost latrine

Progress Update : 17/03/2019
In progress
phase 1
pdamapp1
24.818401900028217,93.87271571159386
24.8077464,93.915087
4.4374030620139
0
upgradation of urban slum at lamsang np

Progress Update : 13/03/2019
In progress
phase 2
pdamapp1
24.818401900028217,93.87271571159386
24.8157868,93.8771438
0.53315873792543
0
Upgradation of slum Lamsang ,Taothong & Lamdeng Khunou

Progress Update : 27/03/2018
Ongoing
1
pdaapp3
24.818401900028217,93.87271571159386
24.79767603,93.92490608
5.7495586411738
0
Construction of storm water drainage at imphal city

Progress Update : 20/03/2018
in progress
phase II
pdamapp1
24.818401900028217,93.87271571159386
24.8224173,93.8691056
0.57625595665412
0
construction of low cost latrine & shelter upgradation

Progress Update : 20/03/2018
in progress
phase II
pdamapp1
24.818401900028217,93.87271571159386
24.8209856,93.8704129
0.36951189051871
0
construction of low cost latrine & shelter upgradation

Progress Update : 20/03/2018
in progress
phase II
pdamapp1
24.818401900028217,93.87271571159386
24.8224173,93.8691056
0.57625595665412
0
construction of low cost latrine & shelter upgradation

Progress Update : 20/03/2018
in progress
phase II
pdamapp1
24.818401900028217,93.87271571159386
24.8216036,93.87072
0.40901962575089
0
construction of low cost latrine & shelter upgradation

Progress Update : 20/03/2018
in progress
phase II
pdamapp1
24.818401900028217,93.87271571159386
24.8203676,93.8701057
0.34227339080495
0
construction of low cost latrine & shelter upgradation

Progress Update : 20/03/2018
in progress
phase II
pdamapp1
24.818401900028217,93.87271571159386
24.8160082,93.8763562
0.45367749718003
0
construction of low cost latrine & shelter upgradation

Progress Update : 20/03/2018
in progress
phase II
pdamapp1
24.818401900028217,93.87271571159386
24.8096454,93.8815822
1.3223839237682
0
construction of low cost latrine & shelter upgradation

Progress Update : 20/03/2018
in progress
phase II
pdamapp1
24.818401900028217,93.87271571159386
24.8096454,93.8815822
1.3223839237682
0
construction of low cost latrine & shelter upgradation

Progress Update : 20/03/2018
in progress
phase II
pdamapp1
24.818401900028217,93.87271571159386
24.8096454,93.8815822
1.3223839237682
0
construction of low cost latrine & shelter upgradation

Progress Update : 20/03/2018
in progress
phase II
pdamapp1
24.818401900028217,93.87271571159386
24.814418,93.8698065
0.53143562638183
0
construction of low cost latrine & shelter upgradation

Progress Update : 20/03/2018
in progress
phase II
pdamapp1
24.818401900028217,93.87271571159386
24.814418,93.8698065
0.53143562638183
0
construction of low cost latrine & shelter upgradation

Progress Update : 20/03/2018
in progress
phase II
pdamapp1
24.818401900028217,93.87271571159386
24.8096454,93.8815822
1.3223839237682
0
construction of low cost latrine & shelter upgradation

Progress Update : 20/03/2018
in progress
phase II
pdamapp1
24.818401900028217,93.87271571159386
24.8223825,93.8538259
1.957042719049
0
construction of low cost latrine & shelter upgradation

Progress Update : 20/03/2018
in progress
phase II
pdamapp1
24.818401900028217,93.87271571159386
24.8224173,93.8691056
0.57625595665412
0
construction of low cost latrine & shelter upgradation

Progress Update : 20/03/2018
in progress
phase II
pdamapp1
24.818401900028217,93.87271571159386
24.8284147,93.8604758
1.6628936913035
0
construction of low cost latrine & shelter upgradation

Progress Update : 20/03/2018
in progress
phase II
pdamapp1
24.818401900028217,93.87271571159386
24.83318,93.8709555
1.6527439471089
0
construction of low cost latrine & shelter upgradation

Progress Update : 20/03/2018
in progress
phase II
pdamapp1
24.818401900028217,93.87271571159386
24.8333615,93.8556726
2.3926499283119
0
construction of low cost latrine & shelter upgradation

Progress Update : 20/03/2018
in progress
phase II
pdamapp1
24.818401900028217,93.87271571159386
24.8370526,93.8429107
3.6533271472922
0
construction of low cost latrine & shelter upgradation

Progress Update : 20/03/2018
in progress
phase II
pdamapp1
24.818401900028217,93.87271571159386
24.833782,93.8547036
2.4956791325404
0
construction of low cost latrine & shelter upgradation

Progress Update : 19/03/2018
in progress
phase II
pdamapp1
24.818401900028217,93.87271571159386
24.8238951,93.8652808
0.96748998655973
0
construction of low cost latrine & shelter upgradation

Progress Update : 19/03/2018
in progress
phase II
pdamapp1
24.818401900028217,93.87271571159386
24.8238951,93.8652808
0.96748998655973
0
construction of low cost latrine & shelter upgradation

Progress Update : 19/03/2018
in progress
phase II
pdamapp1
24.818401900028217,93.87271571159386
24.8156553,93.8666709
0.68222286404049
0
construction of low cost latrine & shelter upgradation

Progress Update : 19/03/2018
in progress
phase II
pdamapp1
24.818401900028217,93.87271571159386
24.8156571,93.8667228
0.67745300415649
0
construction of low cost latrine & shelter upgradation

Progress Update : 19/03/2018
in progress
phase II
pdamapp1
24.818401900028217,93.87271571159386
24.8122302,93.8534726
2.0597450962685
0
construction of low cost latrine & shelter upgradation

Progress Update : 19/03/2018
in progress
phase II
pdamapp1
24.818401900028217,93.87271571159386
24.8237589,93.8623569
1.2031776145357
0
construction of low cost latrine & shelter upgradation

Progress Update : 19/03/2018
in progress
phase II
pdamapp1
24.818401900028217,93.87271571159386
24.8216036,93.87072
0.40901962575089
0
construction of low cost latrine & shelter upgradation

Progress Update : 19/03/2018
in progress
phase II
pdamapp1
24.818401900028217,93.87271571159386
24.8216036,93.87072
0.40901962575089
0
construction of low cost latrine & shelter upgradation

Progress Update : 19/03/2018
in progress
phase II
pdamapp1
24.818401900028217,93.87271571159386
24.8224173,93.8691056
0.57625595665412
0
construction of low cost latrine & shelter upgradation

Progress Update : 19/03/2018
in progress
phase II
pdamapp1
24.818401900028217,93.87271571159386
24.83318,93.8709555
1.6527439471089
0
construction of low cost latrine & shelter upgradation

Progress Update : 19/03/2018
in progress
phase II
pdamapp1
24.818401900028217,93.87271571159386
24.8203676,93.8701057
0.34227339080495
0
construction of low cost latrine & shelter upgradation

Progress Update : 19/03/2018
in progress
phase II
pdamapp1
24.818401900028217,93.87271571159386
24.8203676,93.8701057
0.34227339080495
0
construction of low cost latrine & shelter upgradation

Progress Update : 19/03/2018
in progress
phase II
pdamapp1
24.818401900028217,93.87271571159386
24.8203676,93.8701057
0.34227339080495
0
construction of low cost latrine & shelter upgradation

Progress Update : 19/03/2018
in progress
phase II
pdamapp1
24.818401900028217,93.87271571159386
24.8160082,93.8763562
0.45367749718003
0
construction of low cost latrine & shelter upgradation