Progress
 
 
Project Details
DAR-2026-000040
MSPDCL-SASCI-114
Supply & Laying of 11 KV XLPE AI Cable (3x300sq.mm.) for Underground Cabling (1.79x2 km-Double Run)
2025-12-16
POWER (MSPDCL)
Imphal-West
287.48
0.00
State Plan
erection WIP
2 phase
24.823058742272146, 93.95252716220408
Supply & Laying of 11 KV XLPE AI Cable (3x300sq.mm.) for Underground Cabling (1.79x2 km-Double Run) for providing alternate 11 KV Supply to Khuman Lampak Main Stadium from 33/11 KV Khuman Sub-Station under SASCI Scheme.
Progress Update : 2026-03-24
erection WIP
2 phase
PMU3MA1
24.823058742272146, 93.95252716220408
24.8253316,93.9527218
0.25348024970292
Approved
2026-03-24 06:46:26
mspdcladmin
0
cable laying

Progress Update : 2026-03-24
erection WIP
2 phase
PMU3MA1
24.823058742272146, 93.95252716220408
24.8253141,93.9527253
0.25156815545822
Approved
2026-03-24 06:46:37
mspdcladmin
0
cable laying

Progress Update : 2026-03-24
erection WIP
2 phase
PMU3MA1
24.823058742272146, 93.95252716220408
24.8252139,93.9526258
0.2398377328835
Approved
2026-03-24 06:46:48
mspdcladmin
0
cable laying

Progress Update : 2026-03-24
erection WIP
2 phase
PMU3MA1
24.823058742272146, 93.95252716220408
24.8287577,93.9478362
0.79096424882046
Approved
2026-03-24 06:47:01
mspdcladmin
0
cable laying

Progress Update : 2026-03-24
erection WIP
2 phase
PMU3MA1
24.823058742272146, 93.95252716220408
24.8252533,93.9526368
0.24426265438576
Approved
2026-03-24 06:47:41
mspdcladmin
0
cable laying

Progress Update : 2026-03-24
erection WIP
2 phase
PMU3MA1
24.823058742272146, 93.95252716220408
24.8230501,93.9505326
0.2012867747209
Approved
2026-03-24 06:47:55
mspdcladmin
0
cable laying

Progress Update : 2026-02-11
material delivery
phase 1
PMU3MA1
24.823058742272146, 93.95252716220408
24.8649983,93.9787033
5.3592488179567
Approved
2026-03-24 06:48:14
mspdcladmin
0
supply of material

Progress Update : 2026-02-11
material delivery
phase 1
PMU3MA1
24.823058742272146, 93.95252716220408
24.8654339,93.9787575
5.4041194726864
Approved
2026-02-11 09:38:07
mspdcladmin
0
supply of material

Progress Update : 2026-02-11
material delivery
phase 1
PMU3MA1
24.823058742272146, 93.95252716220408
24.8654273,93.9787617
5.4036872766323
Approved
2026-02-11 09:38:02
mspdcladmin
0
supply of material

Progress Update : 2026-02-11
Material delivery
phase 1
PMU3MA1
24.823058742272146, 93.95252716220408
24.8654394,93.9787591
5.4047316929353
Approved
2026-02-11 09:37:55
mspdcladmin
0
Supply of material

Progress Update : 2026-02-04
Supply of material
phase 1
PMU3MA1
24.823058742272146, 93.95252716220408
24.8654403,93.9792969
5.4315983688492
Approved
2026-02-11 07:10:09
mspdcladmin
0
material arrived

Progress Update : 2026-02-04
supply of material
phase 1
PMU3MA1
24.823058742272146, 93.95252716220408
24.8648986,93.9791627
5.3726425691653
Approved
2026-02-11 07:10:20
mspdcladmin
0
Material arrived

Foundation & Inauguration
-
-
-

-
-
-