Progress
 
 
Project Details
DAR-2026-000002
KCG/DARPAN/BLDG/WWH
Construction of Working Womens hostel 17 Cap at Kakching Khullen Kakching District Manipur SH Civil Work
2025-04-15
PWD
Kakching
14900.00
0.00
State Plan
35
1
24.499109047845785,93.97469866275821
EW CC 148 form work Brick work Steel
Progress Update : 2026-01-14
35
1
nh3so4
24.499109047845785,93.97469866275821
24.4989885,93.9750336
0.036443016002053
Approved
2026-01-14 07:25:19
se3pwd
0
work in progress

Progress Update : 2026-01-08
20 pc
1st Phase
8368672997
24.499109047845785,93.97469866275821
24.4993357,93.9749027
0.032577565677713
Approved
0
Earthwork,RCC Foundation,Column,Grade Beam Plinth Beam,Brick Work.

Progress Update : 2026-01-08
20 pc
1st Phase
8368672997
24.499109047845785,93.97469866275821
24.4993357,93.9749027
0.032577565677713
Approved
2026-01-13 14:47:49
se3pwd
0
Earthwork,RCC Foundation,Column,Grade Beam Plinth Beam,Brick Work.

Progress Update : 2026-01-07
15 pc
1st phase
8368672997
24.499109047845785,93.97469866275821
24.4990275,93.9750209
0.03384090810343
Approved
0
Earthwork, RCCFoundation, Column,Grade Beam ,Plinth Beam, Brick work.

Foundation & Inauguration
-
-
-

-
-
-