Progress
 
 
Project Details
DAR-2025-000525
MSPCLC71
Installation of 3Nos. of 33KV line bays for 33/11KV Koutruk S/S & erection of 33KV line from Iroishemba to NSU, Koutruk on turnkey basis
2025-08-20
POWER (MSPCL)
Imphal-West
640.63
640.63
POWER (MSPCL)
Central Sector
100% completed
x
24.80748517734833,93.94173431396518
Amended amount as per Work order No. 4/33kV/Koutruk(NSU)/2025/MSPCL(PURCH)/112-23 dated 13th April, 2026 is Rs. 640.63.
Progress Update : 2026-05-21
100% completed
x
skennedy
24.80748517734833,93.94173431396518
24.8193065,93.8875286
5.6263708934129
Approved
2026-05-22 06:40:33
davidkumar
640.63
33kv iroisemba koutruk line bay at iroisemba ss

Progress Update : 2026-03-13
92.375
xx
mex
24.80748517734833,93.94173431396518
24.8602983,93.8660333
9.635098965686
Approved
2026-03-20 09:18:54
davidkumar
265.02
pole erection,pole muffing and conductor stringing

Progress Update : 2025-12-27
50.54
1
mex
24.80748517734833,93.94173431396518
24.7765247,93.8521571
9.6752336967118
Approved
0
only physical progress of supply and F&I of line portion is taken as against the total progress of the work which works out to be around

Foundation & Inauguration
-
-
-

-
-
-