Progress
 
 
Project Details
DAR-2025-000384
RUSA/25-DI/HalfBrickWallFencingDMU/IW
Construction of Half Brick Wall fencing with M.S. Steel bar for Dhanamanjuri University at D.M. Campus, Imphal
09/07/2018
Education (S)
Imphal-West
3565.35
0.00
RUSA
completed
nil
24.820677502509053,93.94270801370007
Construction of Half Brick Wall fencing with M.S. Steel bar for Dhanamanjuri University at D.M. Campus, Imphal
Progress Update : 27/08/2025
completed
nil
so4.eew-mn
24.820677502509053,93.94270801370007
24.8206238,93.9378905
0.48621330365839
0
western side-01

Progress Update : 27/08/2025
completed
nil
so4.eew-mn
24.820677502509053,93.94270801370007
24.8207933,93.942583
0.018026343406336
0
gate-01

Progress Update : 27/08/2025
completed
nil
so4.eew-mn
24.820677502509053,93.94270801370007
24.8206719,93.9427337
0.0026665229423394
0
northern side-01

Progress Update : 27/08/2025
completed
nil
so4.eew-mn
24.820677502509053,93.94270801370007
24.8206039,93.9428395
0.015590620437776
0
eastern side-01