Progress
 
 
Project Details
DAR-2025-000148
IED/Pukhao/1
Impvt. of Pukhao road
2023-02-23
PWD
Imphal-East
230.00
0.00
State Plan
work completed
final phase
24.969594,94.023506
WBM-II & SDBC
Progress Update : 2025-03-04
work completed
final phase
ae4ied
24.969594,94.023506
25.0012462,94.0272411
3.5394695731537
Approved
2025-03-11 07:04:09
se1pwd
0
impvt. of pukhao road SH-B from km 2.89 to km 5.89

Progress Update : 2025-03-04
work completed
final phase
ae4ied
24.969594,94.023506
24.9813295,94.0228644
1.3064667566561
Approved
0
impvt. of pukhao road SH-A from km 0.00 to km 2.89

Foundation & Inauguration
-
-
-

-
-
-