Progress
 
 
Project Details
DAR-2018-000276
MSPCLC20
Construction of 2x5 MVA, 33/11 kV SS at Sugnu along with association 33 kV line & related civil works on turn key basis under NLCPR
28/02/2014
POWER (MSPCL)
Thoubal
1030.30
840.06
NLCPR
100%
Complete
24.29466,93.87644
Construction of 2x1 MVA, 33/11 kV SS at Sugnu along with association 33 kV line & related civil works on turn key basis under NLCPR
Progress Update : 06/01/2020
100%
Complete
tapan
24.29466,93.87644
24.2943153,93.8784166
0.2039481307517
0
Sugnu

Progress Update : 06/01/2020
Complete
Complete
tapan
24.29466,93.87644
24.2936302,93.8761891
0.11729228637591
0
Sugnu

Progress Update : 22/02/2018
Complete
Nil
tapan
24.29466,93.87644
24.2941754,93.8741159
0.24161601624162
0
100 percent complete

Progress Update : 22/02/2018
Complete
Nil
tapan
24.29466,93.87644
24.2946261,93.8762941
0.015259062983894
0
100 percent complete

Progress Update : 22/02/2018
Complete
Nil
tapan
24.29466,93.87644
24.2941754,93.8741159
0.24161601624162
0
100 percent complete

Progress Update : 22/02/2018
Complete
Nil
tapan
24.29466,93.87644
24.2941754,93.8741159
0.24161601624162
0
100 percent complete

Progress Update : 22/02/2018
100 percent Complete
Nil
tapan
24.29466,93.87644
24.2958117,93.8776758
0.17911834027905
0
100 percent complete