Progress
 
 
Project Details
DAR-2024-001221
COSFOM/RWH/SHOKVAO/PRIMARY SCHOOL
COSFOM/RWH/SHOKVAO/PRIMARY SCHOOL
22/03/2023
FOREST
Ukhrul
0.55
0.55
EAP
Completed
Nil
24.991641474106583,94.26793116331135
Installation of 4000 liters of Roof top rain water harvesting structure at Primary School of Shokvao village
Progress Update : 18/01/2025
Completed
Nil
dfoukhrul
24.991641474106583,94.26793116331135
24.9917783,94.26797
0.015709243304464
0.55
Operational and use by the community